Container facility for a security service in the Taunus: positioned, connected, ready to move in

Fully installed container facility for the plant security service
Positioning by loader crane: container suspended on its way to the installation position

How 3 fitters built a security service accommodation on a military site in around a week – from the levelled base via power, water, drainage and air conditioning to the handover of keys

A plant security service works day and night – and for that it needs accommodation that is more than a roof over its head: sanitary rooms, showers, heating, air conditioning, water and drainage. That is exactly the kind of facility we built – as a container facility on a military site in the Taunus, north of Frankfurt.

The special thing about this job: we were actually only booked to set up the containers. But on a military site you cannot simply bring in half a dozen trades – every company and every person has to be security-vetted in advance. As we had been through this vetting, in the end our mechatronics technicians took over all the trades: base, crane coordination, power connection, sanitary connections, water, drainage, air conditioning units.

One thing mattered most to the client: the plant security team should be able to move back in as quickly as possible. It worked – after around a week the facility was ready for occupancy. What we take on when setting up and dismantling container facilities – from the crane lift to power and water to air conditioning – is described on our page Setting up and dismantling container facilities.

Project profile

Fully installed container facility for the plant security service from outside
The fully installed security service container facility from outside

What is a container facility?

A container facility consists of several room modules that are assembled on site to form a building. The individual containers arrive on the lorry fully fitted out – with windows, doors, electrics and interior fit-out – and are positioned by crane, connected to each other and hooked up to the utilities.

The great advantage: what takes months with a solid-construction building stands here in days. Nevertheless, a fully fledged building is created – in this case accommodation for the 24-hour service of the plant security team, complete with toilets, showers and air conditioning for summer and winter.

For individual steel boxes to become a proper building, quality is decided at three points: the base, the connection between the modules – and the service connections. That is exactly where we started.

Why the base matters most

The short answer: because a container facility stands only as level as its foundation. That is why, before delivery, we created a precisely levelled base of concrete slabs and steel plates – every bearing point at the same height.

That is more than cosmetics: if the connected modules are not exactly in one plane, the frames become distorted. If you have ever worked in a crooked container, you know the consequence – doors do not close properly, windows jam, the transitions between the modules wobble and leak. On our prepared base, by contrast, the containers stand level, firm and wobble-free.

Positioning was done by lorry-mounted loader crane: the containers arrived on lorries and were lifted directly from the vehicle into position. They are slung at the container corner castings – with special container lifting hooks, each rated for 12.5 tonnes capacity. The modules were then bolted to each other and joined into one unit – one of the tensioning connectors between the modules can be seen in the photos.

Container lifting hook with 12.5 t capacity for the corner castings
Container lifting hook with 12.5 t capacity for the corner castings
Underground drainage pipe and frost-protected water line in the excavated trench
Drainage pipe and frost-protected water line with trace heating in the trench

Water and drainage: frost-proof right into the container

Accommodation with showers and toilets needs supply and disposal – and these have to work in winter too. The critical point with container facilities: the lines come from outside and lie much shallower than in a building with a basement. Without protection, the fresh water line freezes at the first frost.

Our solution: we dug trenches and laid the fresh water line with trace heating and insulation. The heating tape lies directly against the line and keeps it frost-free – clearly visible in the photos by the blue-sheathed heating cable spiralled around the black water pipe, additionally protected inside a duct.

The drainage pipes were laid to a fall and placed in a specially introduced sand bed. The sand bed protects the plastic pipes from stones and sharp edges in the ground – during backfilling and over the years as the ground settles. Backfill only once everything has been checked: tightness, fall, position.

We also made the power connection for the facility: the modules are supplied via external plug connections and interconnected – clearly visible in the photos on the top of the containers. So the complete supply really did come from one source – power, water, drainage.

Air conditioning: cooling in summer, heating in winter

A container heats up quickly in summer – and cools down just as quickly in winter. So that the accommodation can be used all year round, we installed two split air conditioning units: indoor units in the day rooms, outdoor units on the container wall, refrigerant lines routed neatly in trunking.

The clever part: modern split units not only cool but work in winter as air-to-air heat pumps – so the system heats efficiently too. For the security service's 24-hour duty this means comfortable temperatures on every shift, whether high summer or frosty night.

Split air conditioning outdoor unit mounted on the container wall
Split air conditioning outdoor unit on the container wall
Tensioning connector joins the container modules into one unit
Tensioning connector between the container modules

Everything from one team – because not everyone is allowed onto this site

Normally several companies share a project like this: one for positioning, one for plumbing, one for air conditioning, one for electrics. That was not possible here. A military site cannot admit any number of companies – every single one would first have to go through security vetting.

We were vetted, we were on site – so we took over. Our mechatronics technicians cover mechanical, electrical and building services work: position containers, connect power, connect water, lay drainage, install air conditioning units and commission them. "Only booked to set up containers" became a complete project from one team.

For the client, this was the fastest solution – no waiting for further vetted trades, no coordination between five companies, one contact. And the security service was able to move back in quickly.

Why Omega Mounting?

Drainage pipe laid in the protective sand bed
Drainage pipe laid in the protective sand bed
Container module suspended from the loader crane on its way to the installation position
Positioning by loader crane: container suspended on its way to the installation position

Conclusion: from bare ground to a building ready for occupation in one week

Base levelled, containers set by loader crane, modules bolted together, power connected, toilets and showers connected, fresh water laid frost-proof, drainage in a sand bed, two air conditioning units installed – and all of this on a site that only vetted companies are allowed onto. Three fitters, one week, one contact: that is how a row of containers becomes ready-to-use accommodation.

If you want to set up, connect or completely fit out a container facility – talk to us.

Request a callback – Omega Mounting GmbH, Rodgau. Your partner for industrial installation and container construction in the Rhine-Main region and the Taunus: Frankfurt, Bad Homburg, Oberursel, Offenbach, Hanau – and throughout Germany.

Project photos

Lorry-mounted loader crane unloading the containers for the security service facility
Positioning the container facility by loader crane on the secured site
Container wall with electrical connections and prepared water line
Connecting the drainage line to the container facility
Fresh water line with compression fitting and trace heating in the trench
Trace heating spiralled around the fresh water line
Excavated service trench along the container facility
Protective box for the pipe penetration on the container wall
Fully installed container facility for the plant security service
Positioning by loader crane: container suspended on its way to the installation position

Are you planning a container facility?

Tell us briefly what you need – we'll come back with an honest assessment.

Free, no-obligation callback

Tobias Schott, managing director of Omega Mounting GmbH, on a construction site in front of scaffolding

About the author

Tobias Schott

Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance

A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. The project diary shows jobs his team has planned and carried out – without client names, but with everything there is to learn from them.

Frequently asked questions

More than just unloading: a load-bearing, levelled base, positioning by crane, connecting and bolting the modules together, and connection to power, water and drainage. Depending on use, sanitary fit-out, air conditioning and heating are added – only then is the facility really ready for occupation.

Because otherwise the modules stand distorted: doors and windows jam, the transitions between the containers wobble and can leak. A level base – on this project made of concrete slabs and steel plates – ensures that the entire assembly stands straight, firm and permanently tight.

With trace heating and insulation: a heating tape lies directly against the fresh water line and keeps it frost-free even at sub-zero temperatures. Together with proper insulation, the water supply works all year round – without having to lay the line deep below the frost line.

The sand bed protects the pipes from stones and sharp edges in the ground. When backfilling the trench and during later ground settlement, stones could otherwise cause pressure points or fractures. Sand surrounds the pipe evenly and beds it securely for the long term.

Yes. Modern split air conditioning units work in winter as air-to-air heat pumps and heat very efficiently. For container facilities this is ideal: one unit for summer and winter, fast-reacting and without additional heating installation.

Yes, regularly. Our fitters go through security vetting for airports, data centers and specially secured sites. On this project that was the decisive advantage: as a vetted company we were able to take over all trades instead of having to bring in further companies.

Yes. Frankfurt, Offenbach, Hanau, the Hochtaunus district with Bad Homburg and Oberursel – the entire Rhine-Main region is right on our doorstep in Rodgau. Delivery, crane coordination and complete fit-out included. And if it is further away: we work throughout Germany.

Yes. On a military site every company and every person must be security-vetted before work starts. Our team had passed that check on this project, which is why we could take over all trades. At airports our fitters are vetted under Section 7 LuftSiG, at nuclear facilities under Section 12b of the German Atomic Energy Act.

Where our fitters already hold the required check – for example the background check under German aviation security law at Frankfurt Airport – there is no extra lead time. For a new restricted site the duration depends on the authority and the site rules, so it should be built into the programme early. Vetted staff save our clients weeks of access lead time.

Yes – that is exactly what happened here. We were booked only to position the containers, but every additional company would have needed vetting. So our mechatronics technicians took over all trades: base, crane coordination, power, sanitary connections, water, waste water and air conditioning. The client had one contact and no waiting time for further vetted trades.