Installation of 32 StopTruck® systems at a logistics center near Leipzig

Project Report: Installation of 32 StopTruck® Systems at a Logistics Center Near Leipzig

Complete installation of truck stop systems, including electrical work and commissioning—all from a single source

Safety in loading zones plays a crucial role in modern logistics centers. Trucks rolling away uncontrollably during loading and unloading can have serious consequences—for people, goods, and operations. That is why more and more companies are turning to modern vehicle restraint systems such as Expresso’s StopTruck® systems.

Omega Mounting was commissioned by an internationally active manufacturer in the consumer goods industry based Omega Mounting to handle the complete installation of 32 StopTruck® systems. The scope of work ranged from mechanical installation to electrical commissioning—a prime example of the professional installation of truck stop systems in the logistics sector.

Montage StopTruck-Anlage Logistikzentrum Leipzig

Attachments

32 pieces

Location

Leipzig

Installation Team

8→3 Technician

Performance

Mechanical + Electrical

A Fast Project Launch Thanks to a Strong Team

The Mounting Crew in Action

For projects of this magnitude, one thing matters above all else: a structured project workflow.

To achieve visible results early on and provide optimal support for the construction process, Omega Mounting began the first week of the project with an eight-person installation team on site, consisting of mechatronics engineers, mechanics, and electricians.

Once the main assembly was complete, the team was deliberately downsized. A well-coordinated team of three then took over the fine-tuning, detailed electrical work, and preparations for commissioning.

This approach made it possible to carry out the project in a cost-effective manner while meeting the deadline.

Montage StopTruck-Anlage Logistikzentrum Leipzig

All services under one roof

Installation of StopTruck® Systems

A major advantage for our client was the comprehensive project management.

Omega Mounting not only handled the mechanical installation of the StopTruck® systems, but also carried out all electrical work on its own.

Precision at every single loading point

Installation of Individual StopTruck® Systems

Each of the 32 loading stations had to be prepared individually and assembled with precision.

During this process, the StopTruck® systems were aligned with millimeter precision, mechanically secured, and then connected to the respective hydraulic units, control panels, and traffic light systems, as well as the signaling equipment.

At the same time, our electricians installed all the supply lines and professionally wired the control systems.

Neat cable routing and installation in accordance with standards were a given—because these systems must function reliably over the long term, especially in day-to-day logistics operations.

Montage StopTruck-Anlage Logistikzentrum Leipzig

Mechanical and Electrical Engineering Combined to Perfection

A major advantage for our client was that Omega Mounting was able to handle both the mechanical assembly and the entire electrical installation.

Our technicians installed all the wiring, assembled the control cabinets, wired the systems, and made all the electrical connections in a professional manner.

This meant there was no need to coordinate additional electrical contractors—a real time and cost savings for projects of this scale.

Successful Commissioning in Collaboration with Expresso

After all installation and electrical work was completed, we conducted the joint commissioning with our client, Expresso.

During this process, all StopTruck® systems were inspected, tested, and successfully put into operation. Thanks to close collaboration, any necessary adjustments could be made directly on site.

The result: a modern loading facility with 32 fully installed and operational vehicle restraint systems, ensuring maximum safety in day-to-day logistics operations. The facility was handed over to the operator on schedule.

Why Companies Choose Omega Mounting

Your advantages with Omega Mounting

Industrial projects require experience, flexibility, and effective coordination.

Omega Mounting supports manufacturers, plant engineers, and industrial companies in the installation of sophisticated technical systems—throughout Germany and across Europe.

Whether it's loading equipment, truck stop facilities, or complex electrical installations, our customers benefit from a well-coordinated team, streamlined communication, and professional project management.

Your Partner for Complex Industrial Installations

On site with you soon - with flexibility and reliability

This project is a striking example of what Omega Mounting stands for: efficiently and reliably executing complex industrial projects—all under one roof.

From the very first screw to successful commissioning, we support projects throughout Germany and across Europe.

Are you planning to install truck stop facilities or other loading systems at your logistics center? Contact us—we’ll handle all the mechanical and electrical aspects of your project under one roof.

100% non-binding & free

Tobias Schott, Geschäftsführer der Omega Mounting GmbH, auf einer Baustelle vor einem Gerüst

Über den Autor

Tobias Schott

Geschäftsführer Omega Mounting GmbH, Rodgau · über 20 Jahre Praxis in Montage und Instandhaltung

Gelernter Mechatroniker und seit 2004 in Wartung, Instandhaltung und Industriemontage zu Hause – zuerst an der Seite seines Vaters, seit 2012 mit Omega Mounting: von der Elektrohängebahn in Frankfurt bis zur Krananlage im Hallenneubau. Plant und leitet als Lifting Appointed Person Hebearbeiten in Rechenzentren und auf Industriebaustellen im Rhein-Main-Gebiet, ist Ausbilder und Prüfer für Krane, Hubarbeitsbühnen und Teleskopmaschinen sowie Sicherheitsbeauftragter. Bei Einsätzen im Ausland kennt man ihn als „German Troubleshooter“ – der, den man ruft, wenn es auf der Baustelle klemmt. Was Qualität heißt, hat er nicht aus einem Handbuch, sondern von seinem Vater gelernt: Made in Germany als Anspruch an die eigene Arbeit, nicht als Etikett. Deshalb steht sie bei Omega Mounting an erster Stelle – vor Tempo und vor Preis. Das Auftragstagebuch zeigt die Einsätze, die sein Team geplant und umgesetzt hat – ohne Kundennamen, aber mit allem, was man daraus lernen kann.

en_GBEnglish