Relocating containers for the DZN aid organisation
Project diary
We did a lot of voluntary work in the Ahr valley after the 2021 floods. The aid organisations there can always count on our expertise and our equipment for their relief work.
In a disaster area not everything can be planned, and the equipment you need is not always there. You make do with what is available and decide each day what is feasible.
Project profile
- Client sector: Aid organisation (voluntary work)
- Location: Ahr valley, after the 2021 floods
- Scope: Stacked sea containers lifted apart with an excavator, moved into position, set down on plates and aligned; ground protection mats laid; access road gravelled and compacted
- Equipment: Excavator, lifting accessories, ground protection mats, tractors and tipper lorries
- Result: Containers in place for the relief work and the access road passable





The sea containers had been stacked with a lorry loader crane. To lift them apart with the excavator on site, we had to choose lifting accessories that made the most of its lifting height. The excavator’s arm was short, so we made up the slings to keep lifting height and sling angle within safe limits.
With the excavator and many hard-working DZN volunteers, we moved the containers into position, set them down on plates and aligned them.
As the photos show, heavy rain in the days before had softened the ground, so we laid ground protection mats along every travel route.
The access road was also made passable with gravel using tractors and tipper lorries, which we then compacted over the following days.
We keep your production running
Our service areas
Follow us on social media
Related guides for this project
About the author
Tobias Schott
Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance
A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. The project diary shows jobs his team has planned and carried out – without client names, but with everything there is to learn from them.