Not every job can be planned. This one reached us on a Sunday evening: a logistics company whose new building was still under construction was running on temporary generator power. During commissioning on the Sunday evening, that generator failed and had to be replaced.
Emergency call-out on a Sunday evening
Project diary
The generator fails
Not every job can be planned. This one reached us on a Sunday evening.
A logistics company whose new building was still under construction was running on temporary generator power. During commissioning on the Sunday evening, that generator failed and had to be replaced.



The pressure came from the start of operations: at 4 am on Monday the first goods were due in and out of the warehouse. The client called and asked whether we could replace the generator. A new unit was already on its way but still had to be connected and commissioned.
We dropped our evening plans and drove to the site. We started with fault-finding and confirmed that the existing standby generator could not be run in that condition – the new unit, as planned, had to go in.
That meant disconnecting all existing cables, draining the oil and coolant and lifting the generator off its drip tray – with very little light. A few torches, floodlights and our van's headlights lit the site.
The new generator was delivered and we set it in position. Its connection panel, from a different manufacturer, had different dimensions from the old one, so the existing cables could not be terminated.
Calls to electrical contractors we work with did not help either – nobody had cable lugs and heat-shrink sleeves that size to hand. We set up a temporary solution with batteries and an emergency supply so that the site could at least start in emergency mode.
We spent the night on the phone and email sourcing the right cable lugs and heat-shrink sleeves, so they were on site the next morning to connect the new generator to the existing cables.



We also connected the fuel lines from the day tank, drove in the earth rods and tested them. The new standby generator went live by Monday midday, and the site ran up to full operation.
Building in redundancy
To stop a single generator failure from halting the site again, we recommended installing and connecting a second standby generator to give redundancy. The client has since done this, so one generator can now fail without stopping operations.
Standby power is our work outside emergencies too: Standby generator installation in data centers shows how the machines get into position.
We keep your production running
Our service areas
Follow us on social media
Related guides for this project
Maintenance & Servicing
Maintenance & Servicing
About the author
Tobias Schott
Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance
A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. The project diary shows jobs his team has planned and carried out – without client names, but with everything there is to learn from them.
Frequently asked questions
Yes. Outside office hours, a WhatsApp message reaches us. On this job the call came on a Sunday evening; we were on site the same evening, found the fault, disconnected the old generator and set the new one in position. We sourced the parts overnight, and the new unit was live by Monday midday.
It depends on the connection. Here we disconnected, drained and lifted out the failed generator overnight and set the new one in position. Because the new connection panel needed larger cable lugs, we bridged with batteries and an emergency supply until the new unit went live on Monday midday. For planned swaps we agree the temporary supply in advance.
With a second generator that can carry the load if the first one fails (N+1). That is what we recommended to the client after this job, and they have since installed it – so a single generator failure no longer stops the site. We handle delivery, positioning and mechanical connection; our own qualified electrician makes the low-voltage connection, and licensed specialist firms handle medium voltage.