Installing a 16 t crane at a height of over 30 m
Project diary
We installed a 16 t crane at a height of over 30 m. Three of our fitters completed the job in one day, working alongside other trades. The client works in the hygiene and healthcare sector, so the site's strict safety and hygiene rules applied throughout.
Project profile
- Client sector: Hygiene and healthcare sector
- Scope: 16 t crane installed at a height of over 30 m, alongside other trades
- Team: 3 fitters
- Duration: 1 day (February 2021)
- Result: Crane installed within the one-day window
Overview
- 24 February 2021
- Height: over 30 m
- Safety rules of the hygiene and healthcare sector observed
- 3 fitters plus other trades
- One-day job
Frequently asked questions
Yes. On this project three of our fitters installed the 16 t crane at a height of over 30 m in one day while other trades worked on site. We coordinate every lift through the lift plan and the site's permit-to-work system, and our appointed person (AP) agrees the sequence and exclusion zones with the site manager in advance.
Our managing director, Tobias Schott, acts as appointed person (AP) for lifting operations. He plans and approves the lifts, and a lift supervisor appointed by him runs them on site. Lift plans are available in German or English and can follow the general contractor’s template. UK readers: this mirrors the AP and lift supervisor roles in BS 7121-1.


We keep your production running
Our service areas
Follow us on social media
Related guides for this project
About the author
Tobias Schott
Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance
A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. The project diary shows jobs his team has planned and carried out – without client names, but with everything there is to learn from them.