Power supply for the DZN aid organisation
Project diary
Relief work after the 2021 floods
We worked for the Dachzeltnomaden / DZN aid organisation and installed the complete infrastructure for Camp 2.0 in Rupperath.
Almost 1 km of cable went underground. We dug the trenches by excavator and partly by hand, laid conduits, installed power distribution boxes and connected everything to the standby generators.
Besides the main 63 A cables, we set up many sub-circuits. Every area needed power: the industrial kitchen, storage and office containers, storage tents and, of course, the campers.
Project profile
- Client sector: Aid organisation (DZN / Dachzeltnomaden), voluntary work
- Location: Rupperath, after the 2021 floods
- Scope: Complete power infrastructure for Camp 2.0: almost 1 km of underground cable, trenches by excavator and by hand, conduits, distribution boxes, 63 A main cables and sub-circuits, connection to standby generators
- Equipment: Excavator, our own cable and distribution stock, vehicles
- Result: Kitchen, containers, tents and campers all supplied with power


Building a camp on a bare meadow
The task was to build a complete camp for the volunteers on a bare meadow. Everyone pitched in, and together we managed what had seemed impossible.
We normally set up power infrastructure on construction sites and at large events. So we were well prepared: we could support the planning, and we had enough material in stock.
You are currently viewing placeholder content from YouTube. To access the actual content, click the button below. Please note that doing so will share data with third-party providers.
More informationFor the Dachzeltnomaden, teamwork comes first. We are proud to still support these people and their remarkable team today.
Marius Althof of Marius Althof Filmproduktion filmed the work and made a clip showing what our crew can do. Thank you, Marius.
We are grateful that our own equipment, vehicles and the know-how of our staff let us support so many relief operations.
We are well equipped for future call-outs.
We will keep supporting our partners and the aid organisations we work with.
Our overview explains how we install standby power systems during normal operation: Standby generator installation in data centers.



We keep your production running
Our service areas
Follow us on social media
Related guides for this project
About the author
Tobias Schott
Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance
A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. The project diary shows jobs his team has planned and carried out – without client names, but with everything there is to learn from them.