The SCR catalyst on a standby generator: how urea reduces nitrogen oxides

By Tobias Schott  · 6-minute read · Updated November 2026

An SCR catalyst reduces the nitrogen oxides in the exhaust of a diesel engine: a urea solution is sprayed into the hot exhaust, and in the catalyst nitrogen and water are formed from it – provided temperature, dosing and installation are right.

Large standby generators in data centers are diesel engines with considerable output. Burning diesel produces nitrogen oxides. Depending on the permit and location, they must be reduced in the exhaust. An SCR system in the exhaust line does this.

Here we explain how exhaust aftertreatment with urea works, which parts it consists of, what the urea supply needs and what matters when installing it in the exhaust line.

What is an SCR catalyst?

SCR stands for selective catalytic reduction. An SCR catalyst is a component in the exhaust line in which nitrogen oxides are converted into nitrogen and water with the help of ammonia.

The ammonia is not carried as a gas. It forms in the hot exhaust from an aqueous urea solution that is sprayed in ahead of the catalyst. The solution is non-toxic, but sensitive to contamination and frost.

SCR systems are familiar from trucks, ships and power plants. In data centers they sit on the standby generators of the backup power system, usually as a large housing between the engine and the silencer.

Key facts

How the SCR catalyst works

Technical drawing of the exhaust line of a standby generator with engine, turbocharger, injection of the urea solution, mixing section, SCR catalyst, silencer and urea tank with dosing unit
From the engine via the injection and the mixing section into the catalyst and on to the silencer – the urea solution comes from its own tank. Graphic: Omega Mounting

The exhaust leaves the engine via the turbocharger and manifold. Three stations follow:

Sensors before and after the catalyst measure the nitrogen oxides. From this the controls calculate how much solution is dosed. Too little means the nitrogen oxides remain. Too much means unused ammonia gets into the exhaust air.

The reaction needs heat. Only when the exhaust has reached a certain temperature does dosing begin. With cold exhaust the solution would not break down completely and would form deposits.

Structure of the catalyst

Technical drawing of an SCR catalyst in section with dosing lance, spray cone, mixer, honeycomb blocks in the housing and nitrogen oxide sensors before and after the catalyst
The dosing lance sprays the solution into the exhaust, the mixer distributes it, and in the honeycomb the nitrogen oxides react to form nitrogen and water. Graphic: Omega Mounting
ComponentTaskWhat matters
Dosing lanceSprays the solution into the exhaust.Clear nozzle, correct spray angle.
MixerDistributes the solution in the exhaust.Firmly seated, free of deposits.
HoneycombCoated surface for the reaction.Undamaged, not blocked.
HousingHolds the honeycombs, guides the exhaust.Tight, insulated, well supported.
SensorsMeasure nitrogen oxides and temperature.Correctly fitted, cables protected.
ControlsRegulate the dosing.Set by the manufacturer.

The honeycombs are ceramic or metal blocks with many fine channels. They are sensitive to impacts. During transport and installation the housing is therefore only slung and set down at the designated points.

Urea supply

Technical drawing of the urea supply with tank in a drip tray, filling connection, heated line, dosing unit and line to the dosing lance
Tank with drip tray, heated line and dosing unit – the solution must neither freeze nor become contaminated. Graphic: Omega Mounting

The urea solution needs its own clean supply.

Urea solution attacks some metals. Copper, brass and galvanised parts do not belong in the line. Contaminated solution blocks filters and nozzles. That is why it is only topped up from clean containers and via closed systems.

Installation in the exhaust line

Technical drawing of the installation of an SCR catalyst in the exhaust line with fixed point, sliding support, expansion joint, insulation, supports and condensate drain
Fixed point, sliding support and expansion joint absorb thermal expansion, insulation protects people and keeps the exhaust warm, a drain removes condensate. Graphic: Omega Mounting

An SCR housing is heavy, hot in operation and connected to a line that expands with heat. Four points matter during installation:

In data centers the generator often stands in a plant room or on a roof. The SCR housing then has to reach its position by crane, installation opening or skidding track. The routes are measured in advance, and slinging points and centre of gravity are taken from the manufacturer's documents.

Maintenance and test runs

Standby generators rarely run. For the SCR system this is a challenge.

During short test runs at low load the exhaust often does not get hot enough. Dosing then does not start or only briefly, and deposits can form in the line. That is why regular runs under real load are important, for example with a load bank.

Maintenance includes checking the dosing lance, filters and sensors, a visual inspection of the honeycombs and replacing the solution if it has been stored too long. Urea solution ages, especially in heat.

Whether and which exhaust aftertreatment a plant needs is set by the permit and emission requirements. Operator, planner and authority clarify this. We do not give legal advice on this.

Typical faults

Most problems on the SCR system have a simple cause.

Deposits on the dosing lance or in the mixing section form when dosing has too often taken place with cold exhaust. They narrow the cross-section and disturb the distribution. A blocked nozzle or a clogged filter in the dosing unit means that too little solution arrives. The controls then report excessive nitrogen oxides.

Error messages also come from the sensors. A sensor that was damaged during installation, or whose cable touches a hot component, gives false readings. Leaking expansion joints or flanges let exhaust into the plant room. This often only shows up during a test run under load.

Many of these faults can be avoided during installation: clean lines, protected sensor cables, a stress-free line and enough distance from hot surfaces.

What we pay attention to

When rigging in and installing SCR systems, we pay attention to the mechanics and to later operation.

Where we use it

During the rigging in standby generators in data centers in the Frankfurt area the interior solution also included the SCR system and the tanks for the urea solution alongside the radiator and exhaust line. The manufacturer carried out commissioning. During the generator overhaul of a backup power system the SCR system is one of the areas kept in view during maintenance. More about our services can be found on the page energy and standby power.

More technology explained

Technology explained

everything that belongs to emergency power in a data center.

Technology explained

how the engine gets rid of its heat.

Guide

our guide to maintenance, repair and replacement.

Do you have questions about how this works on your site?

Are you planning a backup power system with an SCR system or do you need to replace a housing? We take care of rigging in and installation and coordinate with the manufacturer. Request a callback.

Free, no-obligation callback

Tobias Schott, managing director of Omega Mounting GmbH, on a construction site in front of scaffolding

About the author

Tobias Schott

Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance

A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. The Technology explained articles cover the equipment and techniques his team uses every day: what counts on site is in them – what only appears in the brochure is not.