Generator maintenance on a standby power system – removal and lifting back in by mobile crane in the Rhine-Main region

Lifting back in: the overhauled component on the crane hook
Lifting back in: the overhauled component on the crane hook

Standby generator set dismantled, generator lifted out through the installation shaft, overhauled parts reinstalled – all from one contractor

A standby power system has to work precisely when everything else fails. To keep it that way, operators carry out regular maintenance and overhauls – and that is exactly where we come in when things get mechanically demanding.

On this project in a larger building complex in the Rhine-Main region, we dismantled a standby generator set so that its generator could be overhauled. The challenge: the generator had to be completely separated from the engine and taken out of the plant room. The only way out led vertically upwards through the installation shaft, on the hook of a mobile crane.

After the overhaul, the reconditioned components came back the same way: lift in, move into position, install, align – until the generator set was complete again.

Project profile

Service

Why is the generator of a standby power system removed?

The short answer: because a thorough overhaul is not possible on the generator set itself. For maintenance of the generator, components have to be made accessible that cannot be reached in the installed condition.

To do this, the generator is completely separated from the drive engine and removed from the system. Only then can the components be professionally overhauled – before everything is reassembled in reverse order.

Standby power systems are almost always located in plant rooms deep inside the building – designed for operation, not for removal. That is exactly what makes maintenance like this a task for installation professionals.

The standby generator set in the plant room before dismantling
The standby generator set in the plant room before dismantling

The AP’s work begins long before the first lift

If you think the appointed person for lifting operations (AP) only supervises the lift on the day, you greatly underestimate the role. Long before our crew arrives on site, the AP calculates, estimates and checks:

Lift plans are prepared for all of this before the first hands-on step on site. Only when every question has been answered does the actual installation work begin – and it then runs exactly as planned.

The underestimated factor: schedule and dismantling

An exact schedule is decisive for a project like this, and one point is regularly underestimated. Before you can even reach the actual components, a considerable amount often has to be dismantled first – on this project, the complete enclosure of the generator. Hardly anyone thinks of this in advance; an experienced planner allows for it from day one.

In addition, safe transport of the components sometimes needs transport frames made of timber or steel. Our crew builds them directly on site – the photos clearly show the custom-made timber frames on which the assemblies were moved through the building. It is exactly this on-site problem solving that distinguishes a well-practised installation crew from a crew that only brings muscle.

How do you separate a generator from the generator set?

Millimetre by millimetre and under control. In the plant room, we worked with chain hoists on a beam structure above the generator set: the generator was slung, lifted and separated from the engine step by step.

The sequence is clearly visible in the photos: the generator hangs from several chain hoists, is traversed above the base frame and set down under control. The coupling assembly was also removed and prepared for transport.

Space was tight throughout: between the generator set, walls and plant equipment, it sometimes came down to a few centimetres despite the heavy components. Every movement was therefore thought through in advance and carried out slowly, guided and on command.

Then it was on machine skates through the corridors of the building – to the installation shaft.

Custom-made timber transport frame for the heavy assembly
Custom-made timber transport frame for the heavy assembly
Millimetre work as a team – despite heavy components, it comes down to centimetres
Millimetre work as a team – despite heavy components, it comes down to centimetres

The way out: vertically through the installation shaft

The only way out of the building led upwards. We positioned the mobile crane above the installation shaft, and it lifted the heavy components vertically out of the basement.

The pictures show this moment from both perspectives: from below, where our team guided and slung the load in the shaft – and from above, where the crane lifted the packaged generator over the treetops onto the laydown area.

Lifts like this demand exact coordination: at times the crane operator cannot see the load, so every movement is made on signals from our lifting team, coordinated by our AP. Here, safety depends on clear communication.

Moving back in and reassembly

After the overhaul, the reconditioned components came back – carefully packaged, delivered and lifted back into the building through the shaft on the crane hook.

In the plant room, our fitters then reassembled the generator set: position the generator, connect it to the engine, fit the coupling, align and secure everything. In the end, the complete standby generator set was back in place – ready for an emergency.

The generator hovering on the mobile crane above the laydown area
The generator hovering on the mobile crane above the laydown area
Lifting back in: the overhauled component on the crane hook
Lifting back in: the overhauled component on the crane hook

Why Omega Mounting for work on standby power systems?

As an installation company from Rodgau, we combine exactly the skills such projects require:

Conclusion

Separate the generator, bring it through the building, lift it out through the shaft, bring the overhauled parts back and reinstall everything. This project shows the full range of our work: mechanics, lifting technology and logistics, working hand in hand.

For the operator, this meant: one point of contact for the complete mechanical part of the generator maintenance – from the first hands-on step to the fully reassembled generator set.

Planning maintenance or an overhaul of your standby power system?

Whether standby power system, generator set replacement or machine relocation: we take on dismantling, lifting operations, transport and reinstallation – even when the only way is through the installation shaft. From Rodgau, we are quickly on site in Frankfurt, Offenbach, Hanau, Darmstadt and the entire Rhine-Main region.

Before the first maintenance is due, the system first has to get into the building. How that works is shown in our overview Standby generator installation in data centers.

What we regularly maintain on standby power systems – engine, cooling system, AdBlue and SCR system, fuel system with day tank, exhaust system, load test – is set out as a service offering on the page maintenance of standby power systems.

Talk to us – request a callback for your project.

Project photos

Mobile crane lifting the generator assembly over the trees
Standby generator base frame after removal of the alternator
Alternator with fan wheel suspended from chain hoists
Alternator suspended from chain hoists above the base frame
Alternator on chain hoists being lowered into position
View down the installation shaft with the alternator
Standby generator set with the alternator refitted
Omega fitters guiding the alternator on the chain hoist
Wrapped alternator hanging from chains above the enclosure
Alternator in slings next to the engine
Generator room with fan wheel on timber baulks and chain hoists
Two fitters lowering the alternator onto timber baulks with chain hoists
Lifting back in: the overhauled component on the crane hook
Lifting back in: the overhauled component on the crane hook

Planning a similar project?

Tell us briefly what you need – we'll come back with an honest assessment.

Free, no-obligation callback

Tobias Schott, managing director of Omega Mounting GmbH, on a construction site in front of scaffolding

About the author

Tobias Schott

Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance

A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. The project diary shows jobs his team has planned and carried out – without client names, but with everything there is to learn from them.

Frequently asked questions

Many components of a generator are not accessible in the installed condition. For a thorough overhaul, the generator is therefore separated from the drive engine and completely removed. After the overhaul, it is moved back in, installed and aligned.

Through the building’s installation shaft. The components are dismantled in the plant room using chain hoists, transported to the shaft on machine skates and lifted vertically upwards there by a mobile crane. Lifting back in follows the same route in reverse order.

The work begins long before the day of the lift: checking passages and clearances, selecting lifting accessories, sizing lifting equipment such as chain hoists, assessing the load-bearing capacity of the suspension points and preparing lift plans. On site, the AP then coordinates all lifting operations – from slinging and communication with the crane operator to coordination with the building operator.

Because before the actual removal, a considerable amount often has to be dismantled first – such as the enclosure of the generator – and this effort is regularly underestimated. A realistic schedule allows for dismantling, transport, lifts and reinstallation from the start and gives the operator planning certainty.

Yes – the work takes place in the plant room and at the installation shaft and is planned so that the rest of the building’s operations are not affected. Transport routes and crane standing areas are agreed with the operator in advance and secured.

Yes. We take on the complete mechanical part: dismantling, lifting out, lifting the overhauled components back in, reassembly and alignment – all from one contractor, with one point of contact.

Our headquarters are in Rodgau near Frankfurt. Jobs in Frankfurt, Offenbach, Hanau, Darmstadt and the entire Rhine-Main region are our core business, and we work across Germany.

Yes. The overhaul itself is done by the specialist; we handle the mechanical side. We separate the generator from the engine, remove the coupling assembly and prepare it for transport. After the overhaul we reconnect generator and engine, fit the coupling and align everything. We work to the manufacturer’s specification and hand the set over for checking by the manufacturer’s service engineers.

Yes. Where heavy assemblies need it, we build transport frames of timber or steel directly on site. On this job the assemblies travelled through the building on custom-made timber frames – on machine skates along the corridors to the installation shaft. That way even bulky parts get through tight routes without damage and can be slung cleanly on the crane hook.

Yes, if the operator’s redundancy allows it. Before we start, the operator confirms that the remaining gensets cover the load while one set is out of service. We plan the work so the rest of the plant keeps running: transport routes and crane areas agreed in advance, work confined to the plant room and the installation shaft, and the overhauled generator back in and aligned before handover.

EnglishEnglish