Extending a sorting system at Frankfurt Airport: 32 emergency stop buttons and sensors retrofitted

Fully installed emergency stop button on the parcel sorting system
Fully installed and connected: emergency stop button at hand height on the sorting system

How 2 fitters brought an existing parcel sorting system up to the new safety standard in 2 days – mechanically and electrically

A sorting system grows with its tasks – and with every extension, the safety systems have to grow too. At Frankfurt Airport, the existing parcel sorting system of an international express and parcel service provider was extended and brought up to date. For this, numerous sensors and 32 new emergency stop buttons had to be integrated into the existing safety circuit. Omega Mounting took over the complete retrofit: pre-assembly of the mounting brackets, mechanical installation of the emergency stop switches and electrical integration into the system – completed by 2 fitters in 2 days, during the daytime in the system's standstill periods.

Project profile

Yellow emergency stop buttons with red mushroom head before installation
Emergency stop buttons before installation: yellow housings with red mushroom head, tested and prepared

What is a safety circuit on a sorting system?

The safety circuit (emergency stop circuit) is the series connection of all safety-relevant switching elements of a system: emergency stop buttons, guard door switches, pull cords and safety sensors. If an element anywhere in this circuit is triggered – for example an emergency stop button pressed – the entire system stops immediately and in a controlled manner. On a parcel sorting system with long conveyor lines this is decisive: at every point where people work or can intervene, a stop must be within reach in an emergency. If the system is extended or modernised, the safety circuit must therefore grow with it – new sections need new emergency stop buttons and sensors, cleanly integrated into the existing circuit.

Why does a system extension need new emergency stop buttons?

Because safety technology has to fit the system, not the other way round. When a sorting system is converted or brought up to date, walkways, working areas and danger points change. Machinery safety rules require that emergency stop devices can be reached quickly from every position – the photos of this project clearly show how many emergency stop switches were installed in the existing safety circuit for this purpose: 32 of them, distributed across the extended system, plus numerous sensors for monitoring the conveyor lines. Only when all elements are installed, connected and tested may the extended system go into regular operation.

Emergency stop housings in a row being prepared for the sorting system
Every housing gets a cable gland, terminals and labelling – series work before installation
Pre-assembled emergency stop housings with cable glands before installation
Pre-assembly in batches: all units prepared and sorted by installation point

How does a retrofit like this proceed?

In three steps – and on this project entirely by one team. First the pre-assembly: for every emergency stop button, a mounting bracket was prepared to suit the respective installation situation on frames, supports and conveyor lines of the existing system. Then the mechanical installation: set the mounting brackets, install the emergency stop switches, everything cleanly aligned and firmly bolted – robust enough for the rough everyday life of a sorting system. Finally the electrical integration: every new button and sensor was integrated into the system's existing safety circuit so that the extended system functions as one continuous safety system. The fact that our fitters master both mechanics and electrics saves a second trade here – and coordination effort.

How do you install on a system that runs every day?

In the shutdown windows – with a plan that fits the system. The sorting system runs to the airport’s timetable, so we worked during the daytime windows in which the system is stopped. This means: material and tools are ready, the installation positions are prepared, the pre-assembly of the mounting brackets is done before the standstill window begins. In this way, 2 fitters completed the entire retrofit in just 2 working days without disrupting sorting operations. We know this way of working from many jobs on conveyor systems – maintenance windows are short, good preparation is everything.

Connecting the cores in the emergency stop housing on the sorting system
Connection in the housing: terminate the cores, fit the strain relief, test the function
Emergency stop button on a stainless steel mounting plate on the frame of the sorting system
Installed emergency stop button on the stainless steel mounting plate on the system frame

Airport experience: working against tight time windows

Frankfurt Airport is familiar territory for Omega Mounting: we maintain conveyor systems in the cargo area, have repaired drive units on high-bay warehouses and repaired security fences in the aviation security area. Our fitters hold the necessary reliability checks and aviation security training and know the procedures at the location – from access control to working in tight time windows alongside ongoing operations. For plant operators this means: no start-up effort, no surprises, reliable execution.

Why Omega Mounting?

Conclusion

32 emergency stop buttons, numerous sensors, 2 fitters, 2 days – and a sorting system whose safety circuit now fits the extended system. Retrofits on existing systems are detail work: every installation situation different, every mounting bracket made to fit, every connection cleanly integrated into the existing safety circuit. If your conveyor or sorting system is to be extended, modernised or retrofitted with safety technology, talk to us.

Request a callback – Omega Mounting GmbH, Rodgau. We work in the Rhine-Main region and throughout Germany.

For more on our airport work – with security-area access and passes in place – see our page Installation and maintenance at Frankfurt Airport (German).

Fully installed emergency stop button on the parcel sorting system
Fully installed and connected: emergency stop button at hand height on the sorting system

Project photos

Fitter connecting an emergency stop button on the sorting system
Fitter wiring the emergency stop housing beneath the sorting system
Fully installed emergency stop button on the parcel sorting system
Fully installed and connected: emergency stop button at hand height on the sorting system

Planning a similar project?

Tell us briefly what you need – we'll come back with an honest assessment.

Free, no-obligation callback

Tobias Schott, managing director of Omega Mounting GmbH, on a construction site in front of scaffolding

About the author

Tobias Schott

Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance

A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. The project diary shows jobs his team has planned and carried out – without client names, but with everything there is to learn from them.

Frequently asked questions

Because the emergency stop devices have to fit the extended system: from every working position, a stop must be quickly reachable in an emergency. New system sections therefore need additional emergency stop buttons that are integrated into the existing safety circuit.

More than just the switch: pre-assemble the mounting bracket to suit the installation situation, mechanically install and align the button, connect it electrically and integrate it into the system's safety circuit – afterwards, the function of the entire circuit is tested.

Yes, with good planning. On this project, work was carried out during the daytime in the system's shutdown windows: pre-assembly and preparation outside the windows, installation and integration within the window. Sorting operations thus remained completely unaffected.

Yes. Our fitters cover mechanics and electrics – from pre-assembly of the mounting brackets to integration of the emergency stop buttons and sensors into the safety circuit. This saves a second trade and interfaces.

On this project: 32 emergency stop buttons and numerous sensors in 2 working days with 2 fitters. Preparation is decisive: if you only start planning in the shutdown window, you lose valuable time.

Yes – from maintenance of conveyor systems in the cargo area via high-bay warehouse repairs to the repair of security fences. From our base in Rodgau we are on site in a short time and meet the access and aviation security requirements.

Yes. Airport ID cards and background checks under German aviation security law (Section 7 LuftSiG) are in place for our fitters, and site inductions are kept current. They pass the checkpoint without a permanent escort, so work on systems in the restricted area starts on schedule rather than at the gate.

Yes. On this sorting system two fitters retrofitted 32 emergency stop buttons and several sensors in two days, working during the scheduled daytime shutdown windows. Mounting plates were pre-assembled before each window began. Because our fitters handle both mechanical and electrical work, no second trade had to be coordinated in the window.