MACHINERY RELOCATION OF AN INJECTION MOULDING MACHINE

The facts:

THE CHALLENGE IN THIS PROJECT WAS THE EXTREME TONNAGE OF THE INDIVIDUAL PARTS

The heaviest part, the moving platen, weighed 95 tonnes on its own. In addition to dismantling the machine, our task was to coordinate the other trades.

The machine stood in the middle of the production hall and had to be broken down into individual parts for transport. Ongoing operations and the set-up work on the other injection moulding machines could not be disrupted. Excellent coordination with the customer and a well-structured schedule were an immense advantage here!

 
Crane lifting a transport crate with machine parts during the machinery relocation of the injection moulding machine
Cargo aircraft being loaded with a transport crate for the international machinery relocation

THE NECESSARY HELP CAME FROM THE NETHERLANDS

The crew was able to lift many machine parts out of the hall with the overhead cranes and the forklift. For the machine bed and the platens, we brought in help from Dutch colleagues.
 
They have sufficiently large lifting equipment in the load range of 100 t and above. Once all parts had been taken out of the hall, they were packed into wooden crates and containers by a packaging specialist for overseas transport. 

Do you also need help with your machinery relocation in the automotive sector?

We know that in the automotive industry, every second of downtime means immense costs.

Our team is thoroughly familiar with all facets and processes of the automotive and supplier industry.

Take a look at our specific services now:

Do you want to move your project forward?

Enquire now for your project.

Services Omega Mounting industrial installation
en_GBEnglish