The preloaded bolted connection: why steelwork is preloaded

By Tobias Schott  · 6-minute read · Updated November 2026

Steel mezzanine under construction – beams and stair in the hall
Beams and stairs of a steel platform under construction: every connection between sections is a bolted joint tightened to the drawings.

A preloaded bolted connection joins steel members with high-strength bolts that are tightened to a specified force – so the plates carry the load through friction or sit so tightly that nothing works loose, even under vibration and alternating loads.

In steelwork, members are bolted, not just welded. Columns, beams, bracing and crane runways arrive on site in parts and are connected there. Many of these connections are preloaded, known in German as HV connections – HV stands for “hochfest vorgespannt”, high-strength preloaded. They are found wherever loads alternate or components vibrate: on crane runways, platforms, machine frames and hall structures. Anyone installing such connections needs more than a spanner: the right material, the right method and clean documentation.

Here we explain the two working principles, the HV bolting assembly, the preloading methods and the typical faults.

What is a preloaded bolted connection?

A preloaded bolted connection is a joint in steel and plant construction using high-strength bolting assemblies that are tightened to a specified preload as designed. In German it is called “HV-Schraubverbindung”.

The assemblies are specified in their own series of standards (EN 14399), and installation on site is governed by the standard for the execution of steel structures (EN 1090-2). The structural engineer decides which connection is needed where. On site, what is in the drawings and installation instructions is implemented.

For installation companies, the preloaded connection is a topic where care becomes visible. Whether a bolt is just hand-tight or properly preloaded cannot be seen from outside. Only marking, checking and records make the difference traceable. That is why clients and inspectors increasingly demand complete proof for steel structures: which connection, which method, which tool, who tightened, who checked. Recording this from the start saves a lot of questions at acceptance.

Key facts

Bearing-type or slip-resistant joint?

Technical drawing in section: bearing-type connection with load on the bolt shank and slip-resistant preloaded connection with friction between the contact surfaces
In a bearing-type connection the bolt shank carries the load, in a slip-resistant connection the friction between the preloaded plates does. Graphic: Omega Mounting

Preloaded bolts work in two ways.

CharacteristicBearing-type connectionSlip-resistant connection
Load transferVia the shank.Via friction between the plates.
PreloadAgainst loosening.Carries the load.
Contact surfacesNo special requirements.Prepared, without paint or only with a suitable coating.
SlipSmall slip possible.No slip.
Typical forStatic loads.Crane runways, vibration, alternating loads.

The difference matters for installation: in slip-resistant connections the surface of the plates determines the load capacity. Paint, oil or rust on the contact surface can reduce it considerably.

The HV bolting assembly

Technical drawing of an HV bolting assembly with hexagon bolt, nut, two chamfered washers and marking on bolt head and nut
Bolt, nut and two washers form an assembly – marked, from one batch and always fitted together. Graphic: Omega Mounting

An HV bolting assembly consists of four parts that belong together.

The parts of an assembly come from one batch and are not mixed. The reason is friction in the thread: it determines how much preload results from a given torque. Mixed parts have different friction, and the preload is no longer right. Preloaded HV bolts are generally not reused.

How the bolts are preloaded

Technical drawing of three preloading methods for HV bolts: torque wrench, snug-tightening followed by turn angle, and washer with indicator protrusions
Torque method, combined method with turn angle or indicator washer – each method brings the bolt to its preload. Graphic: Omega Mounting

There are several methods for preloading. They all have the same goal: a specified preload in every bolt.

Tightening proceeds from the inside outwards so that the plates bed down fully. On large splices this is done in several passes. Every tightened bolt is marked so that none is missed.

The tools matter too. Torque wrenches and power tools must be calibrated, and their setting is checked on a test bolt before work starts. For large bolts, hydraulic wrenches are used, whose pressure is converted into a torque. The conversion table belongs to the tool and is calibrated with it.

Typical faults in preloaded joints

Technical drawing of typical faults in HV bolted connections: paint on the faying surface, washer fitted wrongly, open gap and nut from another batch
Coated contact surfaces, washer upside down, gap between the plates, mixed assemblies – every fault reduces the load capacity. Graphic: Omega Mounting

Most faults do not arise during tightening but before it – in storage, preparation and assembly.

Checking and proving

After preloading, it is checked whether every bolt has its force. How depends on the method.

If a fault is found, not only that one bolt is checked but the whole connection and often other splices from the same shift. Preloaded bolts are not loosened and retightened but replaced if necessary.

Everything goes into the record: which connections, which method, which tool with which calibration, who tightened and who checked. For steel structures subject to acceptance, this record is part of the documentation. Without proof, a connection counts as unchecked even if it was tightened correctly.

Coatings also play a role. Thick paint layers under the head and nut can settle over time and the preload drops. That is why designers specify which surfaces may be coated.

What we pay attention to

For bolted connections in steelwork, we work to the drawings, not by feel.

Where we use it

For a hall at Kassel Airport we installed a steel platform , bolting sections and beams bay by bay. In Aschaffenburg we installed a 16-tonne double-girder overhead crane under the hall roof. In both jobs, safety depends on connections tightened exactly as the drawings require. More on this on our page on Industrial installation.

More technology explained

Technology explained

why 12.9 is not always better.

Guide

tightening torques, friction and flanges.

Technology explained

what holds and what does not.

Do you have questions about how this works on your site?

Do you have questions about how steelwork connections are tightened and documented on your site? We install to the drawings and provide the proof. Request a callback.

Free, no-obligation callback

Tobias Schott, managing director of Omega Mounting GmbH, on a construction site in front of scaffolding

About the author

Tobias Schott

Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance

A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. The Technology explained articles cover the equipment and techniques his team uses every day: what counts on site is in them – what only appears in the brochure is not.