Installation of a hydropower plant in an existing building

Steel plates, a compact crane and chain hoists: how the plant got into the building

Move-in and installation support under difficult site conditions

Not every project goes by the book. When we moved a modern hydropower plant into an existing building, the Omega Mounting installation team faced a particularly tricky task: a dilapidated access road, confined space and a riverbed that had to be drained before installation could even begin.

Our task was to move the individual plant components into the building and actively support the installation team on site – from crane logistics to the final positioning of the components. This project report shows how hydropower plants can be installed successfully even under difficult starting conditions.

Crane during the moving-in of a hydropower plant into an existing building

A challenging starting situation on site

On site: what we found

At the time of the project, the building was still being refurbished. This brought a number of challenges that had to be solved first.

The entrance to the building was in poor condition; in some places the concrete had already worn away. Driving the crane directly across it was therefore not possible.

To ensure the access road could bear the load, large steel plates first had to be delivered and laid out so that both the crane and our machine skates could travel safely over them. Only then could the actual installation begin.

The right crane for confined spaces

The V-Kart crane

A V-Kart crane was used for this project – compared with a conventional mobile crane, it offers several decisive advantages: it is more manoeuvrable, can travel with a raised load and, thanks to its low, compact design, is ideal for jobs with little space.

The drawback on this site: the tyres, which are not designed for off-road use, and the resulting low ground clearance. That is precisely why laying the steel plates beforehand was so crucial – it was what made using the crane on the uneven ground possible in the first place.

Keeping the pit dry and bringing in the intake hopper

Once the access road had been secured with steel plates, installation could finally begin. The first component to be moved in was the hopper.

To do this, it was lifted in from the river side and initially set down on planks. We then used chain hoists to pull it precisely into the opening in the building provided for it.

To prevent water from entering the work area during installation, the riverbed and the building were sealed off with timber shoring and numerous sandbags.

Throughout the entire installation period, pumps kept the area reliably dry.

Safety and shoring on site

Ideal lifting points and ready-made solutions are not always available. On projects like this, it is important to assess directly on site what is feasible – and which safety measures are needed to ensure the components can be lifted in smoothly.

To achieve sufficient stability, several beams were supported with steel props and timber baulks were driven into existing structures at specific points. This ensured that the structure could safely withstand the loads occurring during the rest of the installation.

Bringing in the main components of the hydropower plant

Once the hopper was firmly in place, the actual hydropower plant could be moved in. The biggest difficulty: defining the lifting accessories so that there was enough clearance during the move-in and the load hung exactly level. In addition, the lifting accessories could not be too long, as the distance between ceiling and floor left only limited room for manoeuvre.

Thanks to clearly defined lifting points and their compact design, bringing in the large electric motor and the hydraulic power unit was comparatively straightforward. Positioning the arch was more demanding: it had to be carefully brought into the right position using a round sling and a chain hoist so that it could be fitted precisely.

Securing and handover to the concrete works

Once all components had been aligned and positioned, the last step before final fixing followed: additional supports were installed to hold the plant securely. We also welded on brackets and supports where needed.

The following day, the plant could finally be concreted in and thus permanently anchored in the building.

Why clients choose Omega Mounting

Your advantages with Omega Mounting

Projects like this show what really matters in demanding industrial installations: experience in dealing with unpredictable site conditions, technical know-how in crane and slinging techniques, and the ability to find the right solution quickly on site.

Omega Mounting supports manufacturers, plant engineers and industrial companies with the installation of demanding technical systems – throughout Germany and across Europe. Whether hydropower plants, loading technology or complex industrial plants: our customers benefit from a well-coordinated team that works precisely and safely even under difficult conditions.

Are you planning to install a technical system under demanding site conditions? Get in touch – together we will find the right solution for you, from crane logistics to mechanical completion.

Fitter at the riverbed next to the existing hydropower plant building

Frequently asked questions

We make the access road load-bearing first. Here the driveway was damaged, so we laid large steel plates for the crane and our machine skates. A compact V-Kart pick-and-carry crane worked in the tight space, and we pulled the intake hopper into the building opening with chain hoists from timber bearers.

Whatever the space allows: on this hydropower project a V-Kart crane, chain hoists, round slings and machine skates on steel plates. Inside the building the slings had to stay short, because there was little headroom between floor and ceiling. Where needed, we also bring in partner equipment such as larger mobile cranes or telehandlers – lift plan included.

Tobias Schott, managing director of Omega Mounting GmbH, on a construction site in front of scaffolding

About the author

Tobias Schott

Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance

A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. The project diary shows jobs his team has planned and carried out – without client names, but with everything there is to learn from them.

EnglishEnglish