Installation of 32 StopTruck® systems at a logistics centre near Leipzig

Project report: installation of 32 StopTruck® systems at a logistics centre near Leipzig

Complete installation of truck restraint systems including electrical installation & commissioning – all from a single source

Safety in loading zones plays a crucial role in modern logistics centres. Trucks rolling away uncontrollably during loading and unloading can have serious consequences – for people, goods and operations. That is why more and more companies are turning to modern vehicle restraint systems such as the StopTruck® systems from Expresso.

For an internationally active manufacturer from the consumer goods industry in the Leipzig area, Omega Mounting took on the complete installation of 32 StopTruck® systems. The scope of work ranged from mechanical installation to electrical commissioning – a prime example of the professional installation of truck restraint systems in logistics.

Installation of a StopTruck® system at a logistics centre near Leipzig

Units

32 pieces

Location

Leipzig

Installation Team

8→3 Technicians

Service

Mechanical + electrical

A fast project start thanks to a strong team

The installation crew in action

On projects of this scale, one thing matters above all: a structured project workflow.

To achieve visible results early and support the construction schedule as effectively as possible, Omega Mounting started the first project week with an eight-person installation team consisting of mechatronics technicians, mechanics and electricians on site.

Once the main installation was complete, the team was deliberately reduced. A well-coordinated team of three then took over the final installation work, detailed electrical work and preparation for commissioning.

This approach allowed the project to be delivered economically and on schedule.

Installation of a StopTruck® system at a logistics centre near Leipzig

All services under one roof

Installation of the StopTruck® systems

A major advantage for our client was the integrated project delivery.

Omega Mounting not only handled the mechanical installation of the StopTruck® systems, but also carried out all electrical work itself.

Precision at every single loading point

Installation of the individual StopTruck® systems

Each of the 32 loading points had to be prepared individually and installed with precision.

The StopTruck® systems were aligned with millimetre precision, mechanically fixed and then connected to the respective hydraulic power units, control desks and traffic light systems as well as the signalling equipment.

At the same time, our electricians installed all supply cables and professionally wired the control systems.

Neat cable routing and installation in accordance with standards were a matter of course – because these systems must function reliably over the long term, especially in day-to-day logistics operations.

Installation of a StopTruck® system at a logistics centre near Leipzig

Mechanical and electrical engineering perfectly combined

A major advantage for our client was that Omega Mounting was able to handle both the mechanical installation and the complete electrical installation.

Our fitters installed all cables, mounted the control cabinets, wired the systems and made all electrical connections professionally.

This meant no additional electrical contractors had to be coordinated – a real time and cost advantage on projects of this scale.

Successful commissioning together with Expresso

After all installation and electrical work was completed, the joint commissioning took place with our client, Expresso.

All StopTruck® systems were inspected, tested and successfully put into operation. Thanks to the close collaboration, any necessary adjustments could be made directly on site.

The result: a modern loading facility with 32 fully installed and operational vehicle restraint systems, ensuring maximum safety in day-to-day logistics operations. The facility was handed over to the operator on schedule.

Why companies choose Omega Mounting

Your advantages with Omega Mounting

Industrial projects require experience, flexibility and clean coordination.

Omega Mounting supports manufacturers, plant engineers and industrial companies with the installation of demanding technical systems – throughout Germany and across Europe.

Whether loading technology, truck restraint systems or complex electrical installations: our customers benefit from a well-coordinated team, short lines of communication and professional project delivery.

Your partner for demanding industrial installations

On site with you soon - with flexibility and reliability

This project impressively shows what Omega Mounting stands for: delivering complex industrial projects efficiently, reliably and from a single source.

From the very first screw to successful commissioning, we support projects throughout Germany and across Europe.

Are you planning to install truck restraint systems or other loading systems at your logistics centre? Get in touch – we deliver your project, mechanical and electrical, from a single source.

100% non-binding & free

Tobias Schott, managing director of Omega Mounting GmbH, on a construction site in front of scaffolding

About the author

Tobias Schott

Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance

A trained mechatronics technician, at home in maintenance, servicing and industrial installation since 2004 – first alongside his father, and since 2012 with Omega Mounting: from the overhead conveyor in Frankfurt to the crane system in a new-build hall. As appointed person for lifting operations, he plans and leads lifting operations in data centers and on industrial sites in the Rhine-Main region, is an instructor and examiner for cranes, aerial work platforms and telehandlers, and a safety officer. On assignments abroad he is known as the "German Troubleshooter" – the one you call when things get stuck on site. He did not learn what quality means from a manual, but from his father: Made in Germany as a standard for his own work, not as a label. That is why quality comes first at Omega Mounting – before speed and before price. The project diary shows the jobs his team has planned and carried out – without customer names, but with everything that can be learned from them.

en_GBEnglish