Installing 160 PDCs in a data center – lift and shift across eight data halls in the Rhine-Main region

Packed PDCs at their positions on the protected hall floor
Packed PDCs at their positions on the protected hall floor

Across four levels from basement to second floor, six lift and shift fitters set 160 power distribution cabinets to the millimetre – ready for electrical connection

When a new data center is fitted out, the moment comes when hundreds of cabinets weighing tonnes have to go exactly where they will stand for decades. That moment was our job.

At a data center in the Rhine-Main region we were hired to install all the PDCs (power distribution cabinets): 160 units across 8 data halls, each hall with 20 PDCs in two rows of 10.

Our crew handled the whole mechanical scope. We brought the cabinets into the building and distributed them across four levels – basement, ground, first and second floor – using the heavy-duty lift for the upper floors. We unpacked them from their wooden crates, lifted them off the pallets and set them to laser-surveyed positions, aligned and ready for the electrical contractor to connect afterwards.

Project profile

Service

What is a PDC?

A PDC (power distribution cabinet) is a central power distribution unit in a data center: it takes power from the main LV switchboard and feeds it, under control, to the server racks in the data hall. The cabinets are packed with switching and distribution equipment – heavy and sensitive at the same time.

In modern data centers PDCs stand in long rows along the data halls, connected via cable trays at high level. Their positions are planned to the millimetre: every cabinet must stand exactly below its cable drop and in line with its row.

For the installation that means the same precise sequence 160 times over – without fatigue or routine being allowed to cause mistakes.

How do you distribute 160 PDCs across four floors?

Level by level, cabinet by cabinet. The data halls are spread over four floors – basement, ground, first and second floor – with 40 PDCs on the second floor alone. After delivery, the PDCs in their wooden crates were brought into the building, taken to their level by heavy-duty lift and set down in the data halls.

The photos show the scale: whole rows of transport crates lined up in the halls, with the cable trays already in place overhead. The logistics – which crate goes to which level and hall, and when – were a planning task in their own right. With 160 cabinets, four floors, one heavy-duty lift as the bottleneck and a job lasting several weeks, the material flow had to be sequenced as carefully as the installation itself.

The wooden crates beneath the prepared cable trays
The wooden crates beneath the prepared cable trays

Unpacking and lifting: Smartlift and aluminium gantry

The first step in the build-up was to unpack the PDCs from their wooden crates and prepare everything so they could come off their pallets safely.

Two lifting methods were used. The Smartlift, a compact electric lifting device, picks up and moves the packed cabinets under control. An aluminium gantry with chain hoist raises each PDC off its pallet onto its own feet. The photos show the gantry clearly: the cabinet hangs in round slings on the chain hoist, is raised, the pallet is taken away, and the PDC settles gently onto the hall floor.

This combination is ideal for data halls: compact, quiet, emission-free – and precise enough to move sensitive electrical equipment without vibration.

Laser surveying: millimetre work times 160

Before a single cabinet reached its final position, the entire hall was laser-surveyed. Based on that survey the set-down positions of all PDCs were marked precisely – the marking lines on the floor protection are clearly visible in the photos.

Each PDC was then placed at its position, aligned with its row and positioned exactly under its cable drop. With two rows of 10 cabinets per hall, any deviation shows up immediately – the alignment has to hold over the whole length of the row.

Only when position, alignment and level are right is the cabinet fixed and signed off to the next trade.

Moving the PDC under control on the Smartlift
Moving the PDC under control on the Smartlift
The laser-surveyed hall with marked set-down positions
The laser-surveyed hall with marked set-down positions

A clean interface: preparation for the electrical work

The electrical connections were not in our scope on this job; the electrical contractor made them afterwards. That is exactly why a clean handover mattered: every PDC stood exactly on its surveyed position, aligned and ready for connection to the prepared cable trays.

This split between trades is everyday practice in data center construction, and it only works if each trade hands over exactly what the next one needs. A cabinet standing crooked or in the wrong place would delay the electrical crew at once. Across 160 cabinets there was no rework.

Protecting the finished data halls

As on all jobs in finished data centers the rule was: not a scratch on the floor or on existing equipment. All travel and working routes were laid with protective boards and fleece, and the hall walls were screened off.

All machine movements took place in a controlled way on the protected routes – over several weeks, in eight halls, without a single instance of damage.

Aligned and ready for electrical connection
Aligned and ready for electrical connection
Packed PDCs at their positions on the protected hall floor
Packed PDCs at their positions on the protected hall floor

Why Omega Mounting for data center rollouts?

After CRAH units and load banks, this job is another step in our data center track record – this time a multi-unit rollout over several weeks:

Conclusion

160 PDCs, 8 data halls, 6 fitters, several weeks – and at the end every cabinet stands to the millimetre on its surveyed position, ready for electrical connection.

This job shows a side of lift and shift that is often underestimated: precision at volume. Setting one cabinet accurately is craftsmanship; setting 160 at the same quality is process discipline – and that is what our crews bring to every data center job.

Are you planning a rollout in your data center?

PDCs, CRAH units, load banks or racks: we handle installation, setting and positioning – to the millimetre, documented and handed over cleanly to the next trades. From Rodgau we reach the data centers in Frankfurt, Offenbach and Hanau quickly.

The power supply of a data center also includes the standby power system – how it gets into the building is described under Standby generator installation in data centers.

More about our work in the city, access routes and service areas: Industrial installation in Frankfurt.

Talk to us – request a callback for your project.

Project photos

Data hall with PDCs set in position on the protected floor
PDCs in wooden crates in the data hall
Wrapped PDC cabinets along the protected aisle
Row of transport crates in the data hall
Transport crates next to a column in the data hall
Mini crane lifting a wrapped PDC off the pallet truck
Aluminium gantry with chain hoist lifting a PDC, fitter controlling the load
Wrapped PDC on a pallet with pallet truck next to the mini crane
Unpacked transport frames and crates in the data hall
Packed PDCs at their positions on the protected hall floor
Packed PDCs at their positions on the protected hall floor

Planning a similar project?

Tell us briefly what you need – we'll come back with an honest assessment.

Free, no-obligation callback

Tobias Schott, managing director of Omega Mounting GmbH, on a construction site in front of scaffolding

About the author

Tobias Schott

Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance

A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. The project diary shows jobs his team has planned and carried out – without client names, but with everything there is to learn from them.

Frequently asked questions

A PDC (power distribution cabinet) is a power distribution unit that takes power from the main LV switchboard and feeds it to the server racks in the data hall. PDCs stand in long rows in the data halls and are connected via cable trays at high level.

By heavy-duty lift and lift and shift equipment: the cabinets, packed in wooden crates, are brought into the building, taken to their level – on this job from basement to second floor – and stored in the data halls. For installation they are unpacked and lifted off the pallet onto their feet with a Smartlift compact lifting device or an aluminium gantry.

On this job with an aluminium gantry and chain hoist: the cabinet is slung and raised, the pallet is taken away, and the PDC is set down on the hall floor under control – without vibration or tilting, which matters with sensitive electrical equipment.

Because every PDC must stand exactly below its cable drop and in line with its row. The laser survey transfers the design data onto the hall floor, and every set-down position is marked before the first cabinet goes in. That keeps the alignment right along rows of ten cabinets.

Not on this job – the electrical contractor made the connections. Our task was the mechanical side: installation, setting, alignment and a clean handover to the electrical crew. Depending on the job, our own qualified electrician can take on low-voltage connection work.

Our company is based in Rodgau, in the middle of the Rhine-Main region – one of the largest data center locations in Europe. Jobs in Frankfurt and the surrounding area are core business for us; we take on projects across Germany as well.

Both. On this rollout we laser-surveyed every data hall before the first cabinet went in and marked all set-down positions from the design data on the floor protection. Where the GC provides a grid or setting-out lines, we set the units to those. What matters is one binding reference per hall – that keeps the alignment true along the whole row.

Three things: the layout plan with halls and levels, the quantity with weight and dimensions per unit, and the time frame. Add the heavy-duty lift with capacity and car size, the delivery zone and the permitted raised floor loads. With that we check bottleneck, material flow and load data, suggest a site visit if needed and send a written assessment of sequence, interfaces and documentation.

Yes. Each cabinet is checked against the inspection and test plan the GC sets – identity, position, alignment, level, fixing, photo – and signed off unit by unit before the electrical contractor starts on it. That is the installation contractor’s Level 2A in Cx terms. On this rollout the per-unit sign-off is why 160 cabinets went to the electrical contractor without rework.