Data Center Installation: What's Different for Subcontractors
By Tobias Schott · 24-minute read · Updated October 2026
Installing plant in a data center means working in a building that never stops. Access, cleanliness, floor loads and documentation decide the outcome long before the first bolt is tightened.
You are planning installation work in a data center – CRAH units, power distribution cabinets, generators, fire suppression, pipework – and the tender already shows that the rules differ from a production hall. Every access is registered, every machine checked, every route protected. A subcontractor new to data centers loses hours on day one, the programme on day two and the client's trust on day three.
For a project manager that means stress; for procurement it means variations. Every wait at the security gate, every repair to floor protection and every missing document shows up somewhere. A live data center does not forgive carelessness: a scratch in the raised floor is annoying, a damaged cable in a live data hall is an incident.
This overview guide explains what sets data center installation apart from other industrial installation, from the point of view of a contractor that does both. It covers access and induction, why cleanliness is a technical requirement, how heavy plant gets into the building, what the raised floor can take and which documents are handed over at the end. Five jobs from the Rhine-Main region show what this looks like in practice.
Key points at a glance
- Data center installation almost always takes place in or next to live operation, so protecting the existing equipment takes priority over speed.
- Access list, safety induction and equipment approval need lead time and must be settled before the first working day.
- White space (data hall) and grey space (plant areas) need different floor protection, lifting equipment and access arrangements.
- Combustion engines are normally banned inside the building; lifting and transport equipment must be electric or manual.
- The raised floor carries only the loads approved by the manufacturer and the structural engineer – every point load is calculated or spread beforehand.
- Every lift has a lift plan and is covered by the RAMS; without a permit to work and lift approval, nobody lifts.
- The handover to the next trade is documented: position, alignment, bolting, photos, inspection certificates and snagging list are part of the service.
What is data center installation?
Data center installation is moving in, setting, aligning and mechanically fixing plant in a building whose purpose is the uninterrupted operation of IT systems. Safety, cleanliness and documentation requirements are well above those of a normal industrial site.
This typically includes:
- Computer room air handlers (CRAH units, which cool the data hall)
- Power distribution cabinets (PDCs, which distribute power from the main switchboard to the racks) and busbars
- Standby power systems (diesel generator sets), transformers and UPS systems (uninterruptible power supply)
- Chillers, fire suppression equipment, exhaust and silencer systems, pipework and cable routes
The installation contractor delivers the mechanical part: lift and shift, setting in place, levelling and alignment, bolting and handover. Lift and shift – as data center tenders usually call it – means bringing heavy plant into finished buildings. Electrical connection, the chilled-water side and testing belong to the specialist MEP trades. Commissioning runs in levels, from factory tests (Cx L1) to the integrated systems test (L5); the installation contractor delivers Level 2A – equipment set in place and anchored, ready for the red tag. How we set up these services is shown on our page on industrial installation for data center construction.
Data center or industrial hall: what is different?
Data center installation is different because the building keeps running during the work or is about to go live. Every mistake threatens not one machine but the availability of entire customer systems.
In a production hall, a line can be stopped for installation during a maintenance window. In a data center, cooling, power and fire suppression keep running while a single component is replaced. Redundancy makes the swap possible: spare capacity means one unit can fail or be taken out without disrupting operation – N+1 (one unit more than needed) or 2N (fully duplicated). It also means there is less reserve during the work. That is why every intervention runs through a maintenance window and an operator change request.
This results in three differences that shape everyday work:
- Access is controlled. Every person, tool and machine is registered, checked and either escorted or cleared. Unannounced deliveries do not get in.
- Protection before speed. Floors, walls, cable trays and neighbouring plant are protected before work starts, not repaired afterwards.
- Everything is documented. From the lift plan to the equipment inspection to the handover photo – what is not documented counts as not done.
A subcontractor who treats these three points as normal saves you coordination effort. One who sees them as red tape costs you time.
White space or grey space: where is the work done?
White space is the data hall with the server racks; grey space is the plant areas around it. Each needs different preparation.
White space: the data hall
The white space is where the IT sits: racks in rows, sometimes in enclosed cages, cold and hot aisles, raised floor, cable trays and overhead busbars. Requirements here are at their highest. Dust is a risk to servers, every point load must suit the raised floor, and work above live racks is either banned or tightly controlled.
Grey space: plant and supply areas
The grey space covers CRAH galleries, electrical rooms, UPS rooms, generator halls, medium-voltage rooms, suppression cylinder rooms, pipe basements and roof areas. This is where the heavy plant stands. Floors are mostly solid slabs, loads larger and access routes tighter. Access is often a little less restrictive than in the data hall – but never open.
What the difference means for installation
| Criterion | White space (data hall) | Grey space (plant areas) |
|---|---|---|
| Typical components | PDCs, racks, containment, sometimes CRAH units | Generators, chillers, transformers, UPS, fire suppression, pipework |
| Floor | Raised floor, limited loads | Structural slab, loads per structural design |
| Lifting equipment | Electric or manual lifting devices, machine skates | Machine skates, gantries, chain hoists, mobile crane outside |
| Dust and cleanliness | Highest requirement | High requirement |
| Access | Strict, usually escorted or individually cleared | Controlled, after induction |
| Disruption risk | Directly at live IT systems | To supply systems with redundancy |
State in the scope of works which area the work is in. It affects equipment choice, protection effort and staffing.
How do access and induction work on a data center site?
Access and induction on a data center site usually run in three stages: registering people and machines in advance via the access list, the on-site safety induction, and daily access control through security gates or site passes.
The legal basis is the same as on any construction site. Employers working at the same location must cooperate under the German Occupational Safety and Health Act (ArbSchG) and inform each other about hazards; briefing employees is also a legal duty. UK readers: this is broadly comparable to the coordination duty in MHSWR 1999 reg. 11. Data centers apply these rules more consistently than other sites because operators enforce their own site rules on top. The BAuA practical guide on site set-up states the principle: anyone starting work on a site must be inducted into local conditions at the start, and again when conditions change significantly. An installation job in a data center starts with the induction appointment, not with the delivery.
Registration with lead time
Fitters' names, dates of birth and sometimes ID copies are submitted in advance for the access list. Machines are registered with type, inspection certificate and – for lifting devices – tyres and drive. Allow several working days; a registration on the day of the job almost always fails.
On-site induction
Before the first working day, every fitter receives a safety induction into the site rules: escape routes, alarm procedure, prohibited zones, emergency stops and suppression systems, reporting lines. The site language in many data centers is English, because designers, operators and subcontractors are international. The installation contractor must make sure everyone in the crew understands the induction. If in doubt, the foreman repeats it bilingually in the toolbox talk before the shift. On international sites, we always have an English-speaking supervisor on site.
The operator's induction does not replace the briefing by the fitter's own employer. Germany's technical rule TRBS 1116 treats every new site as first use of the work equipment. So the installation contractor must brief its crew before the first lift in the data center and record the briefing with date, content and names. A simple check for the client: ask for the subcontractor's briefing record alongside the induction attendance list.
Daily access control
Access to the data hall and plant areas is through security gates, site passes or operator escort. Tool and material checks are common, and anyone leaving the building for lunch goes through the check again. We plan this time as working time, not as buffer.
What role does cleanliness play on a data center site?
Cleanliness in a data center is a technical requirement, not a matter of appearance. Dust, swarf and abrasion endanger servers, filters and fire detection, and scratches on floors or existing plant count as damage.
That is why every installation starts with protecting the surroundings. Dust control and floor protection are separate items in the method statement. Routes are laid with hardboard or protective fleece, joints taped, walls draped, cable trays and neighbouring plant covered. Machines run on non-marking tyres. Drilling and cutting happen outside wherever possible, or with extraction. Hot work needs a hot work permit and a fire watch.
Some of what looks like an operator rule is simply the law. The BG BAU/BAuA module on low-dust working points out that under the German Hazardous Substances Ordinance dust must be extracted at source. Dry sweeping or blowing off with compressed air is generally not allowed; the module calls for dust class M extractors. In practice, extraction when drilling and a vacuum instead of a broom are not special operator requests – they are the minimum every quotation must include.
Typical rules subcontractors must follow
- Do not open packaging that sheds particles (wood wool, polystyrene, cardboard dust) in the data hall; unpack in airlock or storage areas.
- No combustion engines in the building; forklifts, lifting devices and cranes are electric or cable-powered.
- No unsecured tools overhead in occupied areas.
- Clean up at the end of every shift, not just at the end of the job.
- Protection stays in place until the next trade has taken over and the work has been signed off.
That sounds like effort, and it is. But the alternative costs more time than any roll of fleece: a complaint about a damaged floor, or a particle alarm from the early fire detection.
How are heavy components brought into the data center?
Heavy plant enters a data center by three routes: by mobile crane through installation openings, shafts or open facades; by goods lift to the upper floors; or horizontally through doors and corridors. Horizontal moves use machine skates, heavy-duty dollies and lifting devices – almost always combined with one of the other routes. Every door opening, headroom and swept path along the way is surveyed in advance.
Lift and shift means exactly this: taking a piece of plant from the lorry to its position in a finished building without opening up the building. Our service page explains how lift and shift into finished buildings works.
The lift plan
Every lift has a lift plan. It sets out load weight and centre of gravity, lifting points and lifting accessories (round slings, chain slings, spreader beams, shackles) including sling angles and edge protection. It also covers machine positions, load path, clearances and responsibilities. The lift plan is part of the risk assessment under Section 5 of the German Occupational Safety and Health Act, or of the RAMS (risk assessment and method statement) used on data center sites. Lifting accessories are selected, inspected and used in line with DGUV Rule 100-500. Before the actual lift, a trial lift checks that the load hangs steadily.
Lifting equipment inside the building
Because diesel engines are banned inside the building, lifting equipment is electric or manual. Typical kit:
- Electric lifting devices, winch stackers and hydraulic machine skates
- Chain hoists on aluminium gantries, hydraulic gantries and mobile gantry cranes
- Spider cranes in electric mode – compact crawler cranes with extendable outriggers that turn almost on the spot on rubber tracks
Which equipment fits depends on weight, door openings, turning radii, headroom and floor loading.
Electric lifting equipment needs power – and in existing buildings where that comes from is a question in itself. The BG BAU/BAuA module on site utilities rules out supplying a site directly from the building's fixed installation. Power from existing sockets may only be drawn through a portable residual current device (PRCD-S), and RCDs must be tested every working day. Clarify in the interface list whether the client provides a site distribution board or the installation contractor brings its own with PRCD-S.
One person gives the commands
On every lift, exactly one person gives the commands and everyone else follows them. Our appointed person for lifting operations (AP, in BS 7121 terms) plans and approves the lift; a lift supervisor appointed by the AP runs it on site and can stop it at any time. Slingers and signallers work on the lift supervisor's command. Nobody stands in the load area or under a suspended load, and the load is secured by two independent means before anyone touches it. That is not just a data center rule but the basic rule of every lifting operation.
How a CRAH unit replacement runs step by step is set out in our separate CRAH unit replacement checklist.
What floor loads can the raised floor take?
The raised floor can take exactly the distributed and point loads that the manufacturer and structural engineer have approved for that installation. The installation contractor must know these values before the first skate rolls onto it.
A raised floor consists of panels on height-adjustable pedestals; the void below carries cables and sometimes cold air. Its capacity is given as a permitted distributed load (in kN/m²) and a permitted point load per panel. A unit on four small rollers creates four point loads with high contact pressure, which can exceed the limit quickly even when the total weight looks harmless.
How we handle floor loads
- Obtain load assumptions: the permitted loads of the raised floor and structural slab, in writing, from the client or structural engineer.
- Calculate the load path: Check the machine's weight, number of rollers and roller diameter against the permitted point load. If it is exceeded, lay load spreading plates – steel or aluminium plates that spread the load over several panels and pedestals.
- Check pedestals: No missing panels along the route, no loose pedestals, no open cable cut-outs.
- Check alternatives: Some loads do not belong on the raised floor at all; then the route runs over the structural slab or a temporary track of load spreading plates.
- Secure the standing position: If the unit stands permanently on the raised floor, it needs a support frame or plinth that carries the load down to the structural slab. That is a design task, not an installation decision.
The same care applies to structural slabs in the grey space. A solid slab has limits too, and a generator on machine skates creates loads the structural engineer must have confirmed. Checking the floor loading before every job is not excessive caution: Germany's technical rule TRBS 2111 Part 1 requires the suitability of a lifting device or crane to be checked again at every place of use, and names load spreading plates as a way to achieve it. We use our own load spreading plates – raised floor panels are never used as packing.
What must an installation contractor document and hand over?
In a data center, the installation contractor documents every step that is safety-relevant or that the next trade relies on. The documentation package is handed over in order with the completion sign-off.
Before the job
- Risk assessment or RAMS for the specific task
- Lift plan for each lift
- Inspection certificates for all machines and lifting accessories (periodic inspection by a competent person under the German Industrial Safety Ordinance)
- Qualification certificates (crane operators, slingers, MEWP and forklift operators)
- Induction attendance list
During the job
- Daily visual check of machines and lifting accessories, recorded
- Toolbox talk and permit to work for each working day
- Photos of the protective measures before work starts
- Deviations, stoppages and near misses with cause and solution
At handover
- Position and alignment of each unit (installation record, survey record where required)
- Bolting and torque record where required
- Photos of the installed unit and the neighbouring existing plant
- Snagging list, completion sign-off and handover record to the next trade
This documentation also protects you as the client. If a question about the position or condition of a unit comes up later, the evidence is in the as-built records.
Data center installation: what safety culture does the operator expect?
A data center expects a safety culture in which every fitter may stop work when something is not right – and that counts as a strength, not a delay.
It shows in the small things. In the toolbox talk before the shift, the crew goes through the day's sequence and its risks. Any change to the planned sequence is reported before it happens. Whoever finds a damaged lifting accessory takes it out of service, even if that delays the lift. Near misses are reported, not hidden. PPE is worn in full, including fall protection wherever there is a fall risk.
Formally, this rests on what applies anyway: risk assessment, briefing, employer duties under DGUV Regulation 1 and, on larger projects, the health and safety plan under the German Construction Site Ordinance. Data centers add permits to work, induction and site rules. A contractor that applies the legal basis properly rarely struggles with them.
For buyers: do not just ask for certificates, ask how they work in practice. A contractor who can tell you when they last stopped a lift, and why, has the culture you need.
Project examples
Five jobs from our project diary show how these principles work in the Rhine-Main region.
160 power distribution cabinets in eight data halls
In a data center in the Rhine-Main region we 160 PDCs moved in and installed. Eight data halls with 20 cabinets each, in two rows of ten, on four levels from basement to second floor. Six lift and shift fitters were on site for several weeks. The cabinets went up by goods lift and were lifted off their pallets with an electric lifting device or an aluminium gantry with chain hoist. Before setting out, every hall was laser-surveyed and every set-down position marked. All routes were under protection boards and fleece, and the walls were draped. Result: not a scratch on floors or existing plant, and no rework across 160 cabinets.
Replacing a CRAH unit in a live data center
In a data center in Frankfurt we replaced a CRAH unit during live operation. The heat exchanger of the old unit was damaged, its fin pack torn open down to the copper tube. One supervisor and three lift and shift riggers needed two working days. The new unit went from the lorry up to the second floor. Two synchronised compact lifting devices then moved it through the narrow aisles of the CRAH gallery next to the data hall and set it to the millimetre. Heavy modules of the old unit, such as the fan section, were moved on hydraulic machine skates. All routes were covered with protective fleece and taped down, access was through security gates and locked doors, and RAMS and lift plans were approved before the start.
Retrieving a spider crane from the finished basement
At a data center in Raunheim, a spider crane brought into the basement during the structural phase was still down there. The building had been completed around it, and its last job was setting CRAH units. Then it had to come out – through a shaft occupied by a construction hoist that could not be dismantled, two centimetres short of the upright clearance. Four fitters retrieved the spider crane from the basement in a single day. Survey and route planning through the fitted-out basement, a lift plan, and electric operation on a long power cable because the diesel engine was banned in the data center. Travel with operator and banksmen at several positions, timber baulks under the construction hoist to spread the load, and angled slinging with an adjustable chain to deal with the missing two centimetres. Finally, the tower crane lifted it up through the shaft.
240 nitrogen cylinders for the suppression cylinder room
In the Frankfurt area, for a specialist fire protection contractor, we installed the cylinder room of a nitrogen gas suppression system. Steel cylinder racks, pipework connected to the existing distribution network and 240 nitrogen cylinders in six banks of 40. Each cylinder was connected to the manifold with valve, pressure gauge and high-pressure hose, at an operating pressure of around 300 bar. Three fitters, two weeks. Every joint tightened under control and leak-checked, every hose routed free of strain. Design and commissioning lay with the fire protection specialist – the mechanical installation with us.
Retrofitting silencers in generator rooms
In a live data center in Offenbach we installed twelve twin turbo silencers. They are intake silencers for the turbochargers of the standby generators, in generator rooms separated from neighbouring offices by just one street. No crane was available. The parts arrived by lorry, were unloaded in front of the building and taken to the floors by goods lift. In the generator rooms, winch stackers raised them onto base frames over two metres high, where they were aligned and bolted. The connection is welded stainless steel pipework with flexible rubber connectors for vibration isolation. Three fitters, several phases over several weeks. Acceptance included a performance test and a noise measurement at full load.
Five jobs, always the same sequence: survey, protection, lift plan and documented handover. Is something similar coming up for you? Then get in touch with us. A site visit usually settles within an hour which installation route and which lifting equipment suit your building.
What this means for your role
For buyers: Award data center installation on suitability, not only on price. That means references from live sites, inspection and qualification certificates, and a commitment to deliver RAMS and the documentation package in the operator's site language. List floor protection, lift plans, RAMS and handover documentation as separate items in the scope of works. Clarify in the interface list what the client provides – goods lift, power for electric lifting equipment, storage area, escort. Fix lead times and waiting time at the security gate in the contract, otherwise they come back as variations.
For designers: Think about installation routes, openings, door widths, lift capacity, crane standing areas and space for later replacement at design stage. Record the permitted distributed and point loads of raised floor and structural slab in the installation design. Every unit installed today must come out again in a few years – in live operation, with N+1 redundancy. Designing for replacement from the start is covered in our guide to replacing chillers, CRAH units and standby power systems in a live data center.
For project managers and site managers: Before the first working day, settle in a site visit: access, induction, storage and unpacking areas, load paths, permitted floor loads, power for electric lifting equipment and the operator's contacts. Have the lift plans and RAMS submitted before any material is delivered, and tie lift approval to the permit to work. As site manager you brief, coordinate the trades before and after in the work area, and sign off the completed work together with the snagging list. Security checks and gate times belong in the programme as working time.
For maintenance managers: For operators, data center installation is not only new build but repairs in the existing facility. Define the remaining redundancy with which a unit may be taken out of service, and how isolation and lockout/tagout (LOTO) are carried out. Keep load paths, installation openings and permitted floor loads up to date in your plant documentation. Require handover photos, inspection certificates and installation records in a form that fits your asset file and maintenance plan – they are your basis for the next replacement.
For occupational safety specialists and HSE coordinators: Check whether the installation contractor's RAMS reflect the data center: work next to live existing plant, electric lifting equipment with cable routing, point loads on the raised floor, English as site language. Ask who gives the commands on every lift, who holds the authority to stop and how the permit to work and lift plan are linked. Align the operator's induction with the contractor's briefing so that no fitter hears two sets of rules. Make sure near misses are reported.
For facility managers and operators: You set the framework in which an installation job succeeds or fails: the change process with change request and maintenance window, proof of redundancy, access list, gate times, permitted floor loads, power for electric lifting equipment and unpacking areas outside the data hall. Name a contact who is reachable during the job, issues permits to work and grants approvals. Keep a fallback ready in case the maintenance window is not enough. Ask for the handover documentation in a form that fits your building file – it is the basis for every later replacement and audit.
Data center site start checklist: template on request
The data center site start checklist sums up on one page what must be settled before the first working day:
- Access: people, ID badges, vehicles
- Induction: date, language, participants
- Material: delivery window, unloading and storage area, unpacking area
- Machines: type, drive, tyres, inspection certificates, power connections
- Protection: floor protection, wall protection, covering of existing plant
- Documents: risk assessment or RAMS, lift plans, qualification certificates
- Contacts: operator, general contractor, specialist trades, emergency
Project managers use it to go through the preparation with the installation contractor point by point; buyers use it to check a quotation for completeness. Request the data center site start checklist via our contact form – keyword “Data Center Site Start”.
Why Omega Mounting?
Omega Mounting is based in Rodgau, south-east of Frankfurt, in the middle of the Rhine-Main data center market. The jobs in Frankfurt, Offenbach and Raunheim linked above are not one-offs but our everyday work – from multi-unit rollouts to replacements in live operation to retrofits without a crane. Our workshop in Rodgau makes transport frames, load spreading plates and brackets when the standard solution does not fit. You can reach us by phone or WhatsApp when a replacement has to fit a maintenance window at the weekend or at night. For standby power systems we also offer maintenance and servicing after handover – and if you award industrial installation for a data center in Frankfurt, Hanau or Darmstadt, you get a single point of contact for move-in, installation, lifting equipment and later maintenance – with short distances in the Rhine-Main region and documentation that is ready at the next replacement.
Conclusion
In a tender, data center installation is often a single line item. Behind it lies a different way of organising the work, even if the mechanics are rarely harder. Access, cleanliness, floor loads, lifting equipment without combustion engines and complete documentation are not extras – they are part of the installation. A subcontractor who has taken this on board delivers on time and without rework; one who underestimates it creates waiting time and variations. If you are planning installation work in a data center, send us the floor plan, the component list with weights and your preferred date. We will come back with an honest assessment of what needs to be settled before the first working day.
Further reading: How a transformer gets into an existing building: Transformer replacement in existing buildings. What a maintenance contract needs to cover: data center maintenance contracts.
Further reading: New in the knowledge base: Installing an extinguishant cylinder room and Fitting a silencer to a generator.
Planning a move-in, installation or maintenance in the Rhine-Main region?
Tell us briefly what you need – we'll come back with an honest assessment.
Free, no-obligation callback
You may also be interested in these guides
About the author
Tobias Schott
Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance
A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. He writes these guides from that practice: what works on our sites is in them – what exists only on paper is not.
Frequently asked questions
The live environment: cooling, power and fire suppression keep running while the installation takes place. That means controlled access with induction and escort, a formal permit to work rather than a verbal go-ahead, and consistent protection of raised floor and existing plant. Add electric rather than diesel lifting equipment and a documentation package that records every lift and every inspection.
White space is the data hall with racks, raised floor and cable trays – the area with the strictest rules on dust, floor loading and access. Grey space is the plant areas around it: generator halls, electrical rooms, CRAH galleries, suppression cylinder rooms, pipe basements. Floors there are solid and access is controlled but less restrictive. State the work area in the scope of works, because it decides equipment, protection effort and staffing.
Exhaust fumes, soot and particles endanger filters, early fire detection and IT equipment, so combustion engines are normally banned in data centers. Lifting and transport equipment is electric or manual: spider cranes on a power cable, electric lifting devices, chain hoists on gantries, winch stackers and machine skates.
The lead time depends mainly on the access list, induction and document review, not on the installation itself. People and machines must be registered, and inspection certificates, lift plans and RAMS approved before material is delivered; the operator's change request must also be approved. Allow several working days to a few weeks, depending on operator and scope, and fix the time in the contract.
A lift plan sets out load weight and centre of gravity, lifting points, lifting accessories with capacity and sling angle, machines and their positions, the load path and clearances, the cordoned-off load area and the responsibilities. It is part of the risk assessment or RAMS and is briefed to the crew in the toolbox talk before every lift.
Yes. We write RAMS and lift plans in English, or bilingually where the site needs it, and use the GC’s templates where they exist. They are submitted for approval before any material arrives – GC-run sites usually expect RAMS around three weeks ahead. Each lift plan states load weight, lifting points, lifting accessories, crane or machine position and exclusion zone, and is briefed to the crew in the toolbox talk.
Capacity depends on design, panel type and pedestal grid and is stated by the manufacturer as permitted distributed and point loads. There are no universal values. The installation contractor must have the values in writing before the job and check the contact pressure under every roller against them. If needed, load spreading plates or a route over the structural slab solve the problem.
Level 2A (L2A). We rig equipment into place, anchor and align it, remove transport restraints, wedges and lifting eyes where applicable, and record its condition with photos. That is what the red tag requires – and only the commissioning agent (CxA) issues it. Energisation (L2B, yellow tag) and functional testing from L3 onwards are carried out by the electrical contractor, the manufacturer and the CxA.
Yes. As installation and lift and shift subcontractor we have quoted and worked under NEC, JCT and FIDIC subcontract forms. The subcontract can follow the form of your main contract; quotation, qualifications and RAMS are prepared in English. On sites in Germany, German occupational safety law still applies alongside the contract.
Yes. On data center sites we work under the general contractor’s or operator’s permit-to-work system and site rules. Our fitters are registered in advance, complete the induction before their first working day and pass access control every day. We submit our risk assessment and method statement (RAMS) beforehand in your format, in English or German. Our own briefing as the employer supplements your induction; it does not replace it.