Multi-unit rollouts in data centers: how data hall installation stays on programme

By Tobias Schott  · 24-minute read · Updated October 2026

Packed PDCs at their positions on the protected hall floor
A rollout starts with the material flow: packed distribution cabinets already stand at their future positions.

A rollout of identical units in a data center succeeds through a stable rhythm, a planned material flow and a check on every unit – not through speed. Fix these before the first lift and you hand over without rework.

A data hall rollout stays on programme when the bottleneck sets the pace, deliveries follow the installation sequence and every unit is checked and signed off before the next trade starts. You have 20, 80 or 160 identical units in front of you: power distribution cabinets, racks, air handling units, cylinder banks of a suppression system. None of them is a big installation job on its own. Together they decide whether the data hall is handed to the electrical or cooling contractor on time – or whether the next trades wait for a few misaligned units and the programme starts to slip.

The trap in rollouts is that they look simple. On the first cabinet everyone is focused, by the fiftieth it is routine, by the hundredth carelessness creeps in. Meanwhile the material flow runs through a single heavy-duty lift, storage space in the data hall (the white space) is scarce, and the raised floor is already finished and accepted.

This guide answers the three questions behind every rollout: how to sequence it, how to organise material flow and storage, and how to keep quality and accuracy the same on every unit. It follows on from our overview guide on data center installation and is written for project managers and buyers who award or manage a rollout.

Key points at a glance

What is a multi-unit rollout in a data center?

A rollout is the repeated delivery, setting and handover of many identical units in data halls, following a defined, sequenced plan. Typical units are PDCs (power distribution cabinets), which distribute power from the main LV switchboard to the server racks. Others are racks in rows and cages, busbars above the rows, CRAH units (computer room air handlers) or the cylinder banks of a gas suppression system.

The difference from a one-off installation is neither the weight nor the lifting equipment. A mistake happens not once but potentially 160 times, and a delay on one unit holds up the whole chain behind it. A rollout is a process, not a lift. In the programme it is a sequence of its own between the trade before (raised floor, trays) and the trade after (electrical, cooling).

In data center construction, this repetitive lift and shift work is a package in its own right – moving heavy plant from the lorry to its final position. Setting PDCs is the most common case. What is generally different for subcontractors in a data center is covered in our foundation guide on data center installation: access and induction, dust control, white space and grey space (data hall and plant areas), live environment, English as site language. Here we cover what a multi-unit rollout adds.

Why do rollouts fail even though every unit is simple?

Rollouts fail through many small frictions, not one big mistake. A cabinet stands a centimetre out of line, the next crate comes out of the lift an hour late, the fleece on the route has slipped by day three, the next trade asks which units are signed off. Each friction costs minutes; over weeks it costs days.

We see three causes again and again:

The fix is not more people but a sequence that settles these three points before the first lift.

How do you plan the sequence of a rollout?

Explanatory graphic: data center rollout – the chain from sequenced delivery via the buffer, the heavy-duty lift as bottleneck and interim storage on each level to installation and sign-off per unit
Know the bottleneck and you can plan around it – in data halls often the heavy-duty lift, with buffers before and after it. Graphic: Omega Mounting

Plan the sequence from the bottleneck: find the slowest station in the chain and align every other station to it. In data halls the bottleneck is rarely the installation crew; it is usually the heavy-duty lift, the delivery zone or the number of lifting devices.

Breaking the chain into stations

A rollout is a repeating chain of stations: delivery, bringing into the building, vertical transport and interim storage in the hall, unpacking, lifting off the pallet, moving and positioning, then levelling, fixing, checking and sign-off. Each station has a duration and a capacity. Lay them side by side and you see at once where material piles up and where people wait.

Identifying the bottleneck

On our rollout of 160 PDCs across four levels – basement, ground, first and second floor – the bottleneck was a single heavy-duty lift. Once that is clear, the rest follows: the lift runs continuously with a buffer of crates in front of it, each level has an interim storage area behind it, and the crew works from that buffer. The crew never waits for the lift, and the lift never waits for the crew.

Fixing the order of halls

Technical drawing in plan view of four data halls: start with the hall connected first, next trade connecting released units, buffer of at least half a hall, installation front at the bottleneck’s pace, crates already in position
The installation front works ahead, the next trade follows – with a buffer of at least half a hall in between so the teams do not get in each other’s way. Graphic: Omega Mounting

The order of halls is a coordination question for the site meeting. Start with the hall the electrical contractor wants to connect first, and spread halls across levels so that the lift stays evenly loaded. A buffer of at least half a hall between installation and the next trade stops the two crews getting in each other's way.

Do not plan away the buffers

A rollout over several weeks needs slack for late deliveries, lift breakdowns and access delays – and for permits to work, the operator's written authority per area and day, which take time. Experience shows that a sequence planned without buffers loses its rhythm at the first disruption and never recovers. Every milestone in the programme therefore needs a fallback.

How do you organise material flow and storage in the data hall?

Give every unit a fixed route and a fixed interim storage place from lorry to final position – before the first vehicle arrives. In a rollout, the material flow on site matters as much as the installation itself. In a finished data hall space is the scarcest resource, and anything not planned gets in the way.

Sequenced delivery instead of bulk delivery

Delivering everything at once sounds efficient but blocks the delivery zone and forces interim storage that does not exist. It is better to sequence deliveries so that material arrives in the order it is installed. On the installation of generators and load banks at a Frankfurt data center, we sequenced five heavy-haulage deliveries so that each low-loader could be unloaded by mobile crane as soon as it arrived. The principle is the same for cabinets and containers: delivery follows the installation sequence, not the other way round. The BG BAU/BAuA information sheet on traffic routes and storage areas makes the same point: on tight sites, avoid interim storage and coordinate deliveries so that escape routes stay clear. For procurement, delivery sequence and storage areas belong in the interface list, not in the improvisation of week one.

Interim storage where the unit will stand

The best interim storage place in a data hall is the unit's final position. On the PDC rollout, the cabinets in their wooden crates were set down in the halls directly below the prepared cable trays they would later be connected to. That saves a second move inside the hall, and the next trade can see what the row will look like before anything is unpacked. The information sheet sets one condition: any slab used for storage must be checked for its capacity first. In a data hall that means the raised floor's load rating must also cover the full crate on its pallet.

Packaging as a material stream of its own

Everything that comes in must go out again: wooden crates, pallets, film, edge protection. In the data hall, packaging is also a fire load and a trip hazard. Plan a return route with fixed collection points and a removal rhythm that matches the installation sequence – otherwise the buffer behind the lift fills with empty crates instead of full ones. What looks like tidying is actually waste law: the BG BAU/BAuA information sheet on waste requires separate collection under the German Circular Economy Act in permanently labelled containers – wood, film and cardboard apart – plus a named person responsible and a written arrangement where several companies share containers. For buyers, that is the template for a clear line item in the scope of works.

Floor loads and routes

Raised floors in data halls – floors on pedestals with cables and air below – have limited point and distributed loads. Where a unit stands, where it is stored and which route it travels must suit the floor's load rating. What counts is the pressure under each wheel, not the total weight. Load spreading plates and hardboard spread the load and protect the surface; they are part of material flow planning, not decoration.

The wooden crates beneath the prepared cable trays
Interim storage in the hall: the crates stand where the cabinets will stand – below their cable drop.
The laser-surveyed hall with marked set-down positions
Surveyed once, set 20 times: the marks on the floor protection are the reference for every unit in the hall.

How do you keep accuracy the same across hundreds of units?

Create one binding reference per hall and set every unit against it. Measuring each unit against walls, neighbours or cable drops adds up errors; a single reference does not pass them on.

Laser survey of the hall as reference

On the PDC rollout, every hall was fully laser-surveyed before a single cabinet reached its final position, and all set-down positions were marked on the floor protection. Each PDC was then set on its mark, aligned with its row, set plumb and positioned directly below its cable drop. With two rows of ten cabinets, any misalignment shows at once – the reference prevents it.

One lifting method for every unit

Technical drawing in four steps: lifting frame with chain hoist and round slings lifts the cabinet, pallet removed, cabinet set down on its own feet, battery-powered lifter moves it to the marking
One quiet, emission-free lifting method for the whole series – lifting points and centre of gravity are defined once for all identical units. Graphic: Omega Mounting

Repeat accuracy needs a lifting method that works the same way on every unit. For cabinets in data halls, a compact battery-powered lifting device for picking up and moving, combined with an aluminium gantry and chain hoist, has proved itself. The unit is lifted off its pallet on round slings with edge protection. Lifting points and centre of gravity are fixed once for identical units and apply to the whole series. The pallet is removed and the cabinet sets down on its own feet. The method is quiet, emission-free and low in vibration – and it is the same for the 160th cabinet as for the first.

Standard method statement and roles

A rollout needs a written method statement with fixed roles: who operates the lifting device, who slings and guides the load (slinger), who directs (signaller/banksman), who checks position and alignment, who records. For the operator of the electric forklift or lifting device, this is more than organisation. Germany's technical rule TRBS 2111 Part 1 requires written authorisation for operating industrial trucks. So ask the subcontractor not only for the operator's licence but for the authorisation for this specific machine. The method statement is part of the risk assessment under Section 5 of the German Occupational Safety and Health Act, submitted on data center sites as RAMS. Repeated lifting and positioning brings its own hazards: fatigue, crush points between units, and manual handling during unpacking.

Rotation against routine

Concentration does not last all day. We rotate tasks within the crew so that nobody makes the same movement for eight hours, and the person checking a unit is not the person who has just set it. A second check on every unit is basic practice in a rollout, not an extra. Rotation has a limit: TRBS 1116 ties authorisation to the specific work equipment, so every fitter who rotates must be briefed and authorised for every station. That is why we fix the rotation in advance.

How does quality control per unit work?

Overview: data center rollout – eight checkpoints per unit, from identity and condition through position, alignment and level to fixing, surroundings and records, with the time of each check
Every unit gets its own record with eight checkpoints – only then does it go to the next trade. Graphic: Omega Mounting

Quality control runs per unit against a fixed checklist; completing it triggers sign-off to the next trade – not in bulk per hall at the weekend. Only when position, alignment and level are right is the unit fixed and signed off.

The checkpoints per unit

CheckpointWhat is checkedWhen
IdentityRight unit in the right position according to the layout planBefore lifting
ConditionTransit damage, packaging, feet, connection areaOn unpacking
PositionLocation against the survey markAfter set-down
AlignmentLine with neighbouring units in the rowAfter set-down
LevelPlumb and height, relation to the cable dropAfter set-down
FixingAnchoring or connection to the installation specificationBefore sign-off
SurroundingsFloor protection intact, no damage to neighbours or traysBefore sign-off
DocumentationPhoto, record, label, sign-off noteBefore sign-off

Benchmark installation per hall

Technical drawing: first unit of the hall under the cable outlet inspected jointly by installation, next trade and site management for position, spacing and connection area, then the following units released one by one
The first unit of each hall is inspected by everyone involved together – after that, each unit is released individually. Graphic: Omega Mounting

The first unit in every hall is checked together with the next trade and the GC's site manager – a benchmark installation; on Cx-managed sites the CxA can attend. Does the position match the cable drop, is the connection area facing the right way, is the spacing to the next unit what the electrician needs? The benchmark makes sure the reference is right before it is copied 19 times.

Sign-off as handover to the next trade

The sign-off per unit is the real interface of a rollout – the handover to the next trade in miniature. On the PDC rollout, the electrical connections were not in our scope; the electrical contractor made them afterwards. So every cabinet had to stand exactly on its surveyed position, aligned and ready for connection to the prepared cable trays. Across 160 cabinets there was no rework – because each unit was checked as it was set, not at the end via a snagging list.

Which records does a rollout need per unit?

Explanatory graphic: data center rollout – three levels of installation records: record per unit, hall overview with sign-off status, and daily report with shift handover
Three levels of records: the record per unit triggers sign-off, the hall overview shows status without follow-up questions, and the daily report lets the next shift start without explanations. Graphic: Omega Mounting

A rollout needs a record per unit that brings together identity, position, checks, sign-off and photos – and an overview per hall that shows the status at a glance. In a rollout, the records are not paperwork; they are the control system.

The record per unit

Every installation record contains the unit's design reference, its position, the checkpoints and results, the inspector's name, and date and time, plus at least one photo of the unit in its row. For units with bolted joints or connections, the installation steps are added, such as torques in the torque record or leak checks. How these records feed into commissioning is described in our guide to commissioning from the installation contractor's side. Commissioning runs in levels, from factory tests (Cx L1) and the installation contractor's L2A sign-off to the integrated systems test (L5).

The overview per hall

A hall overview – on paper at the hall door or digital – shows for every position: delivered, stored, set, checked, signed off. It tells the next trade without follow-up questions what it may work on, and tells the project manager whether the sequence is holding.

Daily report and shift handover

A rollout that runs for weeks depends on a clean end to every shift. The daily report records which units were signed off, where material stands, which disruptions and near misses occurred and what comes first next morning. Whoever takes over the shift needs no explanations, just this list – the shift handover is part of the sequence.

What changes for floor protection and safety in a multi-unit rollout?

Explanatory graphic: data center rollout – four daily control tasks: floor protection, risk assessment for repeated tasks, briefing and toolbox talk, and access and permits to work ahead of the sequence
A rollout over weeks finds every weak point a two-day job never reaches – so floor protection, risk assessment, briefing and permits are checked every day, not set up once. Graphic: Omega Mounting

In a multi-unit rollout, floor protection and safety are a daily control task, not a one-off set-up. A rollout over weeks finds every weak point a two-day job would never reach.

Keeping floor protection intact for weeks

Finished, accepted floors and walls must not get a single scratch. On the PDC rollout, all routes and work areas were covered with protection boards and fleece, and the hall walls were draped. The difference from a one-off job: boards shift, fleece tears, tape comes loose. Checking floor and dust protection is therefore part of the daily start routine – over several weeks, in eight halls, without a single instance of damage.

Risk assessment for repeated tasks

The risk assessment under Section 5 of the German Occupational Safety and Health Act (ArbSchG) must reflect what is specific to a rollout: repeated manual handling during unpacking, crush and shear points when setting into the row, fatigue over long periods, and routes shared by lifting devices and following trades. The hierarchy of controls under Section 4 ArbSchG applies: engineering first (lifting device instead of muscle, edge protection), then organisation (rotation, separated routes, cordoned-off load area, breaks), and PPE last. Everyone in the crew has stop authority – whoever sees something stops the work, even on the last cabinet.

Briefing and language

With mixed-language crews and English site rules, the briefing under Section 12 ArbSchG must be in a language everyone understands. TRBS 1116 adds that every new site counts as first use. So the rollout briefing takes place before the first lift in that data hall and is recorded with date, content and names. On a rollout the daily toolbox talk pays off twice: a short briefing on the day's section, features of the hall and changes to the sequence. A few minutes that save many misunderstandings over weeks.

Planning access and permits

Access lists, security gates, escort and permits to work are routine in a data center; on a rollout they become a pacing factor. Apply for the permit for the next hall only when the previous one is finished and you lose days. Permits are applied for ahead of the sequence, and work next to live halls is also coordinated with the operator's maintenance window.

Suppression cylinder room at a data center – rows of nitrogen cylinders of the gas suppression system
240 cylinders, six banks, one sequence: rollouts are not limited to cabinets.

Project examples

Three jobs from our project diary show what a data center rollout looks like in practice – with cabinets, containers and cylinders.

160 PDCs in eight data halls

Six lift and shift fitters, eight data halls, several weeks. During the rollout of 160 PDCs in a data center in the Rhine-Main region each hall received 20 power distribution cabinets in two rows of ten. The halls were spread across basement, ground, first and second floor, with 40 cabinets on the second floor alone. Every hall was laser-surveyed and the set-down positions marked on the floor protection. Each cabinet was lifted off its pallet with a lifting device and aluminium gantry and set in line with its row below its cable drop. Only when position, alignment and level were right was it fixed and signed off to the electrical contractor. The result: no rework on 160 cabinets and no damage to floors or walls.

Five heavy-haulage loads in one day

Shorter but tighter was the sequence for the installation of generators and load banks at a Frankfurt data center. Five heavy-haulage deliveries, one 220-tonne-class mobile crane with 71 tonnes of counterweight, one long working day. A lift and shift manager, a three-person crane crew and five drivers sequenced the deliveries so that each low-loader was unloaded as soon as it arrived. Every lift was set out in advance in the lift plan with load weight, radius, crane position and exclusion zone. The container modules were slung with chain slings, guided with taglines and set into a multi-storey steel structure. Here the pacing factor was not the lift but the order of deliveries – the principle stays the same.

240 cylinders in two weeks

Three fitters, two weeks, 240 nitrogen cylinders. During the installation of a suppression cylinder room for a nitrogen gas suppression system in the Frankfurt area we installed cylinder racks and connected the pipework to the existing distribution network. The cylinders – six banks of 40 – were brought in, secured and connected one by one. At around 300 bar operating pressure, the same points count on every cylinder: valve correctly oriented, gauge readable, hoses to the manifold free of tension and kinks. Every joint was tightened under control and leak-checked. The specialist suppression contractor could then commission the system section by section without rework. Rollouts are not limited to cabinets: it is the same sequence, 240 times.

Three jobs, three types of unit, one principle: find the bottleneck, sequence the material flow, check every unit. Is a data hall rollout coming up? Then get in touch with us. A site visit to look at the lift, delivery zone and storage areas usually settles within an hour which pace is realistic.

What this means for your role

For buyers: Award the rollout as a separate package with a scope of works by unit – a schedule of rates per unit installed and signed off, not a lump sum per hall. An interface list defines what the client provides: delivery, heavy-duty lift, packaging disposal, sign-off per unit. Price waiting time from late permits or lift breakdowns as a provisional sum so that it does not come back as a variation. Ask for the per-unit installation record and references with comparable quantities as evidence of suitability. Our service page on Lift & Shift shows what belongs in the package.

For designers: One reference per hall, one label per position, one interim storage area per level with enough imposed and point load: design for these and you make the rollout possible. Allow door widths and routes wide enough for lifting device plus unit, lift capacity for unit plus lifting device plus pallet, and a return route for packaging. Set the installation sequence so that the trade before (raised floor, trays) and the trade after (electrical) never work in the same area. More about our approach in data center construction.

For project managers and site managers: Identify the bottleneck before you write the programme, and build buffers between installation and the next trade into the sequence. Require a hall overview with sign-off status that can be read without follow-up questions, and agree a benchmark installation per hall with the next trade at the site meeting. As site manager you brief, sign off each hall and receive the completion records. Apply for access lists, permits to work and lift approvals ahead of the sequence, not after it.

For maintenance managers: For you, a rollout does not end with the handover to the next trade but with records you can carry into the maintenance plan and asset file. Require installation record, label and position per unit to be handed over so that every unit can be identified for inspection and periodic testing later. Use the benchmark installation to check access for maintenance and later replacement too – what stands too close in the row stays too close.

For occupational safety specialists and HSE coordinators: On a rollout, the risk assessment or RAMS must hold for weeks, not one day. Check that it covers repeated manual handling, crush points in the row, shared routes and fatigue. Rotation and breaks must be defined as organisational controls, and stop authority must apply to everyone in the crew. Attend a toolbox talk at the start of a shift from time to time and compare the permits to work with the sequence – that is where you see whether the process is real.

For facility managers and operators: A rollout occupies the lift, delivery zone and interim storage areas in your building for weeks. Define in change control when the heavy-duty lift is reserved for installation and which halls in the live environment need special maintenance windows. Clarify where packaging is collected and removed, so that neither fire load nor trip hazards build up in the data hall. The hall overview with sign-off status tells you without follow-up questions which areas you can release for commissioning.

For manufacturers and system suppliers looking for an installation partner: If you deliver your units in quantity to a data hall, the installation partner is your eyes and hands on site. Make sure they turn your installation instructions into a method statement, record transit damage at delivery inspection and provide an installation record per unit that can be matched to your serial number. That makes the factory acceptance test (FAT) and later commissioning easier. A joint benchmark installation with your product manager settles questions before they repeat many times over.

Data center site start checklist: template on request

A rollout rarely fails at the installation but on the first working day: access, briefing, storage space, missing certificates. Our data center site start checklist puts on one page what must be settled beforehand – access, briefing, material and delivery, machines and power connections, protection, documents, contacts. Request it via our contact form – keyword “Data Center Site Start”.

Why Omega Mounting?

We are an installation contractor from Rodgau near Frankfurt and deliver lift and shift in data centers as a stand-alone package – from unloading through bringing in and positioning to the documented handover to the next trade. The jobs linked here show that we can do repetitive work: 160 cabinets without rework, five heavy-haulage loads in one day, 240 cylinders made leak-tight. From Rodgau we reach data centers in Frankfurt, Offenbach, Hanau and Raunheim quickly, and outside office hours a WhatsApp message reaches us. Our workshop in Rodgau makes auxiliary structures, adapters and protection when a rollout needs something you cannot buy. How we work locally is shown on our page on industrial installation in Offenbach (German). In practice: a single point of contact for sequence, material flow, lifting equipment and records – and a crew that keeps the same pace on the 160th cabinet as on the first.

Conclusion

In short: the bottleneck sets the pace, the material flow follows the sequence, one reference per hall keeps every unit accurate, and one record per unit triggers sign-off to the next trade. Fix these four things before the first lift and you hand over without rework – cabinets, containers or cylinders. Floor protection and safety are checked every day on a rollout, not set up once. If you are planning a data hall rollout in the Rhine-Main region, send us the layout plan, the quantity with unit weight and your preferred date. We will come back with an honest assessment of sequence, interfaces and records.

Planning a move-in, installation or maintenance in the Rhine-Main region?

Tell us briefly what you need – we'll come back with an honest assessment.

Free, no-obligation callback

Tobias Schott, managing director of Omega Mounting GmbH, on a construction site in front of scaffolding

About the author

Tobias Schott

Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance

A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. He writes these guides from that practice: what works on our sites is in them – what exists only on paper is not.

Frequently asked questions

A rollout is the repeated delivery, setting and handover of many identical units – such as power distribution cabinets, racks or air handling units – in a planned sequence. The challenge is not the single lift but keeping the same quality for weeks and matching the material flow to the installation.

The bottleneck in the chain sets the pace. In data halls that is usually the heavy-duty lift or the delivery zone, more rarely the installation crew. Once you know the bottleneck, you plan buffers before and after it in the programme, so material does not pile up and people do not wait.

That depends on the unit, the building, the lift capacity and the permits, and can only be stated reliably after a site visit. On our rollout of 160 PDCs across four levels, six fitters needed several weeks. The number per day mattered less than a pace that held every single day.

Because a laser survey per hall creates one reference for all units. Measuring each unit against walls or neighbours adds up errors along the row. Setting against marked positions keeps alignment, plumb and the relation to the cable drop right along the whole row.

Design reference and position, condition on unpacking, position against the mark, alignment in the row, plumb and height, fixing. Add the condition of floor protection and surroundings, a photo, the inspector, the date and the sign-off note. For units with bolted joints or connections, torques or leak checks are added; the record later feeds the as-built file and commissioning.

Per unit, not per hall. Sign-off follows as soon as position, alignment, level and fixing have been checked, and is shown in the hall overview – which keeps the snagging list short. A benchmark installation with the next trade and the site manager at the start of each hall makes sure the reference is right before it is copied many times over.

Yes. For a rollout we recommend a rate per unit installed and signed off rather than a lump sum per hall – it keeps quotations comparable and invoicing clean. The rate covers lifting off the pallet, setting, aligning, fixing and the installation record. Waiting time from late permits or lift breakdowns is best priced as a provisional sum. To price it we need the layout, quantities with unit weights and the programme.

On our rollout of 160 PDCs in eight halls, six lift and shift fitters worked for several weeks – enough, because the heavy-duty lift set the pace. For larger or parallel rollouts we can add around 20 additional fitters. More people only help if the lift, delivery zone and permits keep up, so we size the crews from the bottleneck, not the other way round.

In the data hall, packaging is a fire load, a trip hazard and takes up space you do not have. It needs its own return route with fixed collection points and a removal rhythm that matches the installation sequence. Settle at tender stage who disposes of the packaging.

Yes. The first unit in every hall is set as a benchmark and checked together with the next trade and the GC’s site manager – on Cx-managed sites with the CxA if required. We check the position against the cable drop, the orientation of the connection area and the spacing to the next unit. Only when the benchmark is agreed do we repeat it across the hall, which keeps the snagging list short.