Spider crane recovered from the basement: millimetre work at the Raunheim data center

Spider crane retrieval from the basement of a data center in Raunheim
The spider crane hanging at an angle on its way up

How 4 fitters manoeuvred a mini crane, around which the building had been finished, through the basement and pulled it up the shaft with a tower crane – even though it was 2 centimetres too big

This was a tight squeeze in more than the figurative sense: on this job we used every millimetre available. We were hired to lift a spider crane out of the basement of a data center in Raunheim. A tower crane on site was to help us – so far, so normal.

The problem: the crane had been brought in while the building was still a shell. No partition walls, no fittings, no site hoist in the shaft. Since then the data center had been built on around the crane – and what had rolled in comfortably back then now had to come out again through a fully fitted-out basement.

So it meant planning a route through the basement in advance, measuring everything, drawing up a lift plan with all the details – and in the end it still came down partly to trial and error. This supposedly quick little job turned into a full day’s work for four people.

Project profile

The spider crane hanging from the chain sling in front of the shaft opening with the site hoist
In front of the shaft opening: the spider crane on the chain sling

What is a spider crane?

A spider crane – also called a mini crane – is a compact tracked crane that fits through ordinary doorways and lifts where large cranes can never reach: in halls, basements, courtyards. Its outriggers spread out like a spider’s legs, hence the name. On its rubber tracks it can turn almost on its own axis – worth its weight in gold inside a building – while being gentle on sensitive floors.

Many spider cranes are hybrids: diesel for outdoors, electric drive for indoors. Exactly those qualities made the machine so useful during the construction phase of the data center – and exactly that is why it was now sitting in the basement, long after the building had lost its shell openings.

Why was the crane stuck in the basement in the first place?

Because the building was finished around it. During the shell phase getting it in was easy: no partition walls, no fittings, an open shaft. But with every construction stage the routes got tighter – walls, building services – and by now there was a site hoist in the removal shaft that could not simply be taken out for us.

On top of that: the crane had not been forgotten in a corner – it had been working right up to that moment. We ourselves used it on the job to install CRAH units, the precision air conditioning units that cool the computers in the data center. The spider crane lifted the units onto the so-called fan bases – the substructures with the fans that the units sit on. Only when the last unit was in place was the crane's job in the basement done – and getting it out became a project of its own.

This is a classic on large sites: machines that come in early and are needed inside eventually have to leave again through a much tighter building. Then you need people who measure, plan – and keep their nerve when there are only millimetres between crane and wall.

View from above into the narrow shaft: the mini crane hanging from the four-leg chain sling
Looking down into the narrow shaft of the data center
Centimetre gap between crane and concrete edge – every millimetre used
Every millimetre used: a centimetre gap between crane and concrete edge

The sequence: from route planning to the lift up the shaft

2 centimetres short – and the answer hung on a chain

Sometimes 2 centimetres decide a whole job. Our survey had predicted it, the shaft confirmed it: hanging upright, the crane would not fit through. We could not rebuild the building – so we changed the geometry of the load.

Using an adjustable chain – whose legs can each be shortened individually with shortening claws – the crane was deliberately slung at an angle. A load hanging at an angle needs less room in one direction than one hanging straight: that hand’s breadth of geometry gave us back the missing centimetres. What matters is that the slinging is still properly calculated – centre of gravity, leg forces, protection against swinging. Angled, with us, means controlled angle, not “it will probably hold”.

Slung at an angle on the adjustable chain – that is how the missing 2 centimetres were found
At an angle on the adjustable chain: how the missing 2 centimetres were found
Timber baulks take the load and protect the platform of the site hoist
Timber baulks take the load and protect the site hoist platform

The site hoist that could not be moved

A site hoist cannot simply be dismantled for a day – that would have blown every schedule on the site. So the crane had to go over the hoist, and partly onto its ramp. To make sure the platform survived the machine’s tonnes unscathed, we propped up the hoist and the ramp completely with timber baulks: the timbers take the load and pass it into the floor instead of pressing it into the hoist structure.

Timber baulks are permanent residents on our loading bed anyway – as a safeguard under a suspended counterweight, as a stack under a machine weighing tonnes, or as load distribution as they were here. Unspectacular material that saves structures and schedules at the right moment.

Planning beats panic – and still the moment decides

Of course there was a lift plan beforehand setting out every detail: route, slinging, path of the lift, responsibilities. For lifts inside tight buildings such a plan is not a formality but the basis for everyone involved – our team, the tower crane operator, the site – having the same picture in their heads.

And still, in a basement with millimetre tolerances: the plan gets you up to the obstacle, manoeuvring through it is down to you. An experienced driver, banksmen on every side, a short pause and a rethink before every bottleneck – that is the kind of teamwork you do not learn from a manual but from many jobs of this kind.

A few centimetres between the crawler tracks and the drive motor of the site hoist
A few centimetres between the crawler tracks and the site hoist drive

Why Omega Mounting?

View from below of the crawler tracks of the spider crane hanging at an angle
The spider crane hanging at an angle on its way up

Conclusion: every millimetre used

A spider crane that had rolled comfortably into the shell, a basement full of fittings, a site hoist in the only removal shaft and 2 missing centimetres: a quick little job turned into a full day of precision work for four fitters. In the end the crane hung at an angle on the adjustable chain, the tower crane drew it centimetre by centimetre up the shaft – and the site was able to carry on without interruption.

If a machine at your site is stuck deeper inside the building than the doors allow: talk to us. There is usually a way out – it just has to be measured.

Request a callback for your project now – Omega Mounting GmbH, Rodgau. Your partner for machine moving and industrial installation in the Rhine-Main region: Frankfurt, Rüsselsheim, Raunheim, Wiesbaden – and throughout Germany.

When no mobile crane can reach the installation location, the method decides. The three options for standby power systems are described under Moving in standby generators at the data center.

Photo gallery of the job

Millimetre work in the shaft of the data center – banksmen directing the suspended crane
The spider crane hovering in front of the opening of the removal shaft
Only a few centimetres between the crane boom and the basement wall
Tight passage in the basement: the mini crane between wall and fittings
Fitter checking the lifting accessory at the lifting point of the spider crane
The spider crane on the chain sling right next to the site hoist
Shackle at the lifting point between the crane and the hoist cladding
The mini crane hovering at an angle above the site hoist through the shaft
The spider crane on its way up – pulled by the tower crane
Spider crane retrieval from the basement of a data center in Raunheim
The spider crane hanging at an angle on its way up

Do you have a machine that is stuck?

Tell us briefly what it is about – we will come back to you with an honest assessment.

100% free and without obligation

Tobias Schott, managing director of Omega Mounting GmbH, on a construction site in front of scaffolding

About the author

Tobias Schott

Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance

A trained mechatronics technician, at home in maintenance, servicing and industrial installation since 2004 – first alongside his father, and since 2012 with Omega Mounting: from the overhead conveyor in Frankfurt to the crane system in a new-build hall. As appointed person for lifting operations, he plans and leads lifting operations in data centers and on industrial sites in the Rhine-Main region, is an instructor and examiner for cranes, aerial work platforms and telehandlers, and a safety officer. On assignments abroad he is known as the "German Troubleshooter" – the one you call when things get stuck on site. He did not learn what quality means from a manual, but from his father: Made in Germany as a standard for his own work, not as a label. That is why quality comes first at Omega Mounting – before speed and before price. The project diary shows the jobs his team has planned and carried out – without customer names, but with everything that can be learned from them.

Frequently asked questions

A spider crane is a compact mini crane on crawler tracks whose outriggers fold out like a spider’s legs. It fits through narrow openings, turns almost on its own axis on rubber tracks and lifts where mobile cranes cannot reach – in halls, basements and courtyards. Many models are hybrids: diesel outdoors, electric inside buildings.

With a site survey, route planning and patience: first the whole route is measured and a lift plan drawn up, then the machine is moved through the building to the millimetre with a driver and banksmen and lifted at the shaft by crane. Where the numbers do not fit, tricks like angled slinging help – or something is dismantled, closely coordinated with everyone involved.

Because of the exhaust fumes: combustion engines are off limits in enclosed spaces – all the more so in a data center with sensitive equipment and fire detection systems. So on this job the hybrid crane ran purely on electricity, via a long three-phase cable laid specially for it – whose voltage drop over that length has to be allowed for.

A lift plan documents a crane lift in detail: load data, lifting gear, centre of gravity, path of the lift, positions, responsibilities. For demanding lifts – narrow shafts, site hoists in the way, several parties involved – it is the shared working basis for crane operator, supervisor and installation team.

Change the geometry of the load: on this job it was 2 centimetres too big, so the crane was slung at a controlled angle with an adjustable chain – hanging at an angle it needed less room in the critical direction and fitted through the shaft. The prerequisite is properly calculated slinging with a secured centre of gravity.

By propping with timber baulks: the timbers take the load and pass it into the load-bearing ground instead of bending the hoist’s platform and ramp. That way the site hoist did not have to be dismantled for our job – and the site schedules stayed untouched.

Yes, regularly: this job in Raunheim was already our tenth documented data center reference in the Rhine-Main region – from chiller replacement through SCR systems and fire suppression to machine moving. Our base in Rodgau sits in the middle of the data center corridor around Frankfurt.

en_GBEnglish