Chiller replacement in data centers: design for replacement from day one
By Tobias Schott · 23-minute read · Updated October 2026
Chillers, CRAH units and generators have a far shorter life than the building they stand in. If replacing them in a live facility is not designed in, you pay later with downtime risk, alterations and weeks instead of days.
Chillers, CRAH units and generators will all be replaced at least once while the data center is live – so the route, space and isolation points for that replacement must be designed in from day one. You are designing a data center or an extension, and the delivery and installation of the major plant is covered: chillers on the roof, standby generators on the upper floors, CRAH units in the CRAH gallery. Then the facade is closed, the crane leaves and operation begins. Long before the building reaches the end of its life, the chiller replacement comes up, followed by the CRAH and generator replacements. Each unit has to come out and a new one go in – while the data hall (white space) stays live.
This is what design often underestimates. The installation opening has become a glazed facade, a substation stands on the crane standing area, the heavy-duty lift is too small for the new, larger unit, and the manoeuvring space next to the chiller has been used for extra plant. What was a crane lift in the new build becomes a dismantling job with hot work in the plant areas (grey space) of a live building.
This guide follows on from our overview guide “Data Center Installation: What's Different for Subcontractors” and is written for designers. It shows what chiller, CRAH and generator replacements in a live data center demand of the building: installation routes, openings, slab loads, crane standing areas, spare space, service isolation and redundancy. And how to plan for this from the outset – with examples from our jobs in the Rhine-Main region.
Key points at a glance
- Chillers, CRAH units and generators are replaced at least once in a data center's life – in live operation, not during the build.
- The installation route from the new build must stay usable as a replacement route: openings, shafts, lifts and corridors must not be built over or reduced in capacity.
- Crane standing areas belong in the external works plan, with verified ground bearing capacity, radius and a clear slewing area.
- Manoeuvring and laydown space next to every major unit decides between a replacement in one piece and a dismantling job under a hot work permit.
- Services – water, fuel, exhaust, power, controls – must be isolatable per unit without affecting the neighbouring units.
- Redundancy (N+1 or 2N) is lower during a replacement than in normal operation; the design defines the reserve at which a replacement in a maintenance window is allowed.
- The documentation from the initial installation – load paths, lift plans, weights, lifting points – is the basis for the replacement years later and belongs in the as-built file.
What does designing for replacement mean in a data center?
Designing for replacement means the building allows every major item of plant to be removed and replaced in a live facility – without interrupting supply, without touching the structure and without cutting the unit up on site.
Three things are needed: a route (installation opening, shaft, lift, corridor, crane standing area), space (manoeuvring and laydown area at the unit) and independence – the unit can be isolated electrically, hydraulically and in its controls from the neighbours that keep running. If one of these is missing, the replacement becomes a special project.
The components in question:
- Chillers: Chilled-water units, usually on the roof or in plant rooms, which produce the chilled water together with dry coolers.
- CRAH units: Computer room air handlers that use this chilled water to cool the data hall via cold and hot aisles; they stand in the hall or in the CRAH gallery.
- Standby power systems (gensets): Diesel engine and alternator with radiator, exhaust, silencers, tanks and switchgear – in generator rooms or as containers outdoors.
- Transformers, medium-voltage switchgear, UPS systems, busbars, pumps as further heavy plant in the grey space.
How we install such plant is shown on our page on industrial installation for data center construction.
Why should chiller replacement be designed in from day one?
Because chillers, CRAH units and generators have a far shorter life than the building, and every replacement in a live building happens under conditions the new build did not have – closed facade, live operation, occupied space.
Major building services plant typically reaches the end of its economic life after 15 to 20 years, depending on load, maintenance and technical change. A data center runs considerably longer. Expect every major unit to be replaced at least once – some more often, for example when capacity rises or a refrigerant is phased out.
What changes between new build and replacement
| Condition | New build | Replacement in existing building |
|---|---|---|
| Facade and roof | open or with installation opening | closed, opening must exist or be creatable |
| Crane | tower crane or mobile crane on an open construction site | mobile crane on the remaining standing area, slewing area restricted |
| Operation | no IT load, the GC's (principal contractor's) site rules | live facility, reduced redundancy, maintenance window and operator's permit to work |
| Lifting equipment inside the building | diesel allowed during the structural phase | electric or manual only |
| Areas | empty, site clear | occupied, limited manoeuvring space |
| Documentation | still being produced | must come from the building file |
The right-hand column is what you are designing for. Everything that makes replacement easier there costs little at design stage and saves weeks in operation.
Which installation routes does a data center need for later replacement?
For later replacement, a data center needs at least one permanently usable installation route per major unit: an installation opening in the facade, an installation shaft through the levels, a heavy-duty lift of adequate size or a roof opening – plus the horizontal load path to the final position.
Installation openings in the facade
The simplest solution for generator rooms on upper floors: an opening in the facade, closed with a removable panel in normal operation. Behind it you need a laydown area inside the building where the load is taken off the crane and set onto machine skates. Size the opening with reserve, not to today's unit – the next generation is rarely smaller.
Installation shafts
A shaft through all plant levels with a removable cover at the top lets a mobile crane lower or raise plant vertically. The shaft must stay clear after completion – no construction hoist, no services, no later installations – and the slabs at the shaft edges must carry the transfer loads.
Heavy-duty lift
A heavy-duty lift solves many replacement problems – if lift capacity, car size and door width suit the largest unit that will ever need moving, including lifting device and packaging. A lift that takes the PDCs but not the CRAH unit is no help with the CRAH replacement.
Roof areas for chiller replacement
Rooftop chillers are replaced by mobile crane: the old chiller is lifted out in one piece and the new one set in the same position. This needs a crane standing area from which the radius reaches the furthest unit, and a roof that carries the manoeuvring and set-down. It also needs enough space between units for one to come out without moving its neighbours.
The horizontal load path
From entry point to final position: door widths, headroom, turning circles and swept paths in corridors, thresholds, fire doors, clear height under trays and ducts. Each must suit the largest unit plus lifting device, and the route only stays clear if it is recorded as a load path in the building file.
Which slab and floor loads must be considered for replacement?
For replacement, slabs and floors along the whole load path must carry the point and distributed loads from unit, lifting device and wheels – not just at the final position but everywhere in between, including laydown areas, shaft edges and lift lobbies.
Load path instead of location
Structural engineers design slabs for the static load of the unit. During replacement, the transport load comes on top: the unit stands on a few machine skates or two lifting devices, so its weight is concentrated as point loads on small areas. Add load spreading plates, chain hoists on spreader beams and, when the load is taken off the crane, dynamic effects. Show the load path in the structural load assumptions, with imposed load and permitted point load per section, so that the installation contractor does not have to guess later.
Raised floor in the white space
CRAH units in the data hall stand on or beside the raised floor, which only takes the distributed and point loads approved by its manufacturer. A replacement across the raised floor needs load spreading plates along the pedestal lines or a route over the structural slab. For CRAH units, plan either plinths that carry the load down to the slab or a load path that avoids the raised floor.
Ground pressure outside
Crane standing areas put high loads into the ground through the outrigger pads. The crane hire company calculates the permitted ground pressure and the mats it needs from the load chart, the radius and your information on ground conditions – so the ground must be known and documented. Underground car parks, service runs, cisterns and soakaways beneath the standing area are the classic surprises. The BG BAU/BAuA information sheet on large equipment puts it simply: a crane may only stand on ground with adequate bearing capacity. The outrigger force spreads in the ground at about 45 degrees, and outrigger mats or timber baulks increase the contact area. In the external works plan, show not just the area but what lies beneath it – then the crane hire company can calculate rather than guess when the replacement comes.
Where must crane standing areas be provided at the building?
Crane standing areas must be provided wherever a mobile crane with enough reach can serve every installation opening, every shaft and every roof position – on firm ground that is kept permanently clear, with a free slewing area.
Reach and lifting height
The radius is set by the distance to the facade, the hook height by the height of the entry point. Together with the load weight, they give the load moment the crane must carry under its load chart. Generator rooms on the first and second floors, chillers on the roof: the higher and further, the larger the crane, its counterweight and its standing area. For very heavy loads a tandem lift with two synchronised mobile cranes may be needed, which means two standing areas with space between them.
Keep permanently clear
The crane standing area from the build is often the first area to change use after completion: substation, cooling tower, car park, landscaping with trees, fence with security clearance. Mark crane standing areas in the external works and security plans and protect them against change of use – a standing area with a container on it is not one. If it lies on a public road, every replacement needs a road-space permit (Sondernutzungserlaubnis) and a traffic management order.
Slewing range and load path in the air
Nothing may obstruct the path between crane and entry point: no overhead lines, lighting masts, roof structures or camera masts. For overhead lines the information sheet sets fixed clearances – five metres where the voltage is unknown – and a line later routed over the standing area can make replacement impossible. Check the slewing area against the neighbouring plot too: oversailing it requires the owner's consent. And the wind limit decides whether a roof lift happens on a given day. Germany's technical rule TRBS 2111 Part 1 sets no value; it requires the employer to set the permitted wind speed and to reassess the crane's suitability at every place of use. For your programme, a roof lift needs a fallback day in the maintenance window, and the wind limit is stated in the lift plan in advance.
How lift and shift works from the crane hook to the final position is explained on our service page on lift and shift into finished buildings.
Which spare space and isolation points make replacement easier?
Replacement is easier with manoeuvring and laydown space next to every major unit and with services that can be isolated per unit without affecting the neighbours.
Manoeuvring space at the unit
Removing a unit in one piece needs space: to lift it, turn it, set it on machine skates and move it out. Without that space it has to be cut up – which means hot work in the plant room, a hot work permit, fire watch, extraction, dust control and a longer job. Keep an area next to every major unit at least as large as its footprint, and mark it in the plans as manoeuvring space. It is not a luxury: in operation it is the first place spare parts, ladders and extra equipment end up unless someone protects it.
Laydown area at the entry point
Behind the installation opening or at the shaft edge, the load needs an area where it is taken off the crane, set down, transferred and set on skates – with adequate slab loading and clear height for lifting beam and chain hoists. Plan power for electric lifting equipment there too. The BG BAU/BAuA information sheet on site utilities rules out supplying installation work directly from the building's fixed installation; power from existing sockets is only allowed through a portable residual current device (PRCD-S). A dedicated site power connection at the laydown area saves running a cable drum through three fire compartments on the day.
Service isolation per unit
Every unit should be individually isolatable and lockable (lockout/tagout, LOTO). That means isolation valves in the flow and return of every CRAH unit and chiller, and flanged rather than welded connections at the unit. Each generator needs separable exhaust and fuel connections, its own switch panel and control connections. Whatever can only be shut down together with its neighbour cannot be replaced in a live facility – the operator will not issue a permit to work for it.
Retrofit capability
Not every intervention is a replacement. Silencers, filters, exhaust after-treatment or extra tanks get retrofitted when regulations or neighbours demand it. That needs space above and beside the plant, and a route for parts that travel by goods lift and corridor without a crane.
How is redundancy maintained during a chiller replacement?
Redundancy holds during a chiller replacement if the remaining units carry the full load while one is out – and the design must define the remaining reserve at which a replacement is allowed.
Redundancy means having more units than the load needs, so that one failure does not disrupt operation: N+1 is one spare unit above demand, 2N a fully duplicated system. During a replacement one unit is out as planned; if another fails meanwhile, the reserve may be used up, depending on the design. That is why operators schedule replacements in low-load maintenance windows, approve every intervention through a change request, and want the swap as short as possible.
What the designer should define
- With what remaining reserve may a unit be taken out of service as planned? This decides whether a replacement is possible at any time or only in low-load periods.
- Can temporary units (temporary chillers, hire generators, a load bank for the test run) be connected to restore the reserve during the replacement? That needs external connection points and standing areas.
- How long may the maintenance window last before the reserve must be restored? This decides whether the unit must go in one piece or may be dismantled – and whether a night or weekend window is needed.
What the installation contractor contributes to a chiller replacement
We shorten the time out of service through preparation. The new unit stands ready on the laydown area before the old one is isolated; load path, lift plan and protection are complete in advance, and removal and installation follow straight on. The fallback if the window is not enough is agreed with the operator. The lift plan sets out load weights, centre of gravity, lifting points, lifting accessories, machine positions, load paths and clearances. The risk assessment under Section 5 of the German Occupational Safety and Health Act (ArbSchG) – on data center sites the RAMS – covers every step. After the mechanical handover, the specialist trades commission the unit through start-up and functional tests (Cx L3 and L4) before it counts towards redundancy again.
Preparation includes the inspection certificates. Germany's technical rule TRBS 1201 requires lifting accessories to be inspected annually and checked every working day, and makes clear that an inspection tag only proves an inspection took place – not that the equipment is free of defects today. So on the day of the lift we check crane, spreader beams and round slings once more before the unit leaves its plinth. As operator you are entitled to see these certificates before approving the lift.
What from the initial installation belongs in the building file?
The building file should hold everything needed to replace a unit years later without a new survey: load paths with permitted loads, lift plans from the initial installation, weights, centres of gravity and lifting points, dimensions of openings and lifts, crane standing areas with ground data, and photos of the installation.
The documentation package we hand over
- Lift plans for each lift with load weights, lifting points, lifting accessories, machine positions and load paths
- Installation records with survey, alignment and tightening torques of the installed units
- Photos of the installation, transport frames and lifting points
- Notes on pinch points and features of the load path, closed snagging list
What the designer should add
- Load paths in the structural plan with permissible distributed and point loads per section
- Installation openings, shafts and lifts with clear dimensions and capacities
- Crane standing areas with ground conditions, permitted ground pressure and slewing area
- Manoeuvring and laydown areas as protected areas in the operations plan
- Isolation valves and disconnection points per unit in the services schematic
Whoever replaces a chiller years later will thank you for this file – or pay for its absence.
Project examples
Four jobs from our project diary show what designing for replacement means in practice – in new build and in live buildings.
More than 60 generators installed over three years
How standby generators get into a data center is shown by more than 60 generators we moved in on data center projects over three years: standby generator installation. The heaviest single generator weighed just over 20 tonnes, the heaviest containerised unit 54 tonnes, with ratings of up to 3 MW. The generator rooms were on the first and second floors, and a tandem lift with two 650-tonne mobile cranes raised the loads about 16 metres. Three methods were used: crane lift through an open facade, tandem lift for the heaviest units, and machine skates in closed buildings. Inside the building: no combustion engines, electric forklifts, a lift plan before every lift, a briefed crew, one person giving commands, and loads secured by two independent means. After the lift came radiator, exhaust after-treatment, manifold and exhaust run, coolant, urea solution and fuel lines, tanks and control cabinet – up to a system ready for commissioning. For designers: every one of these units will one day leave by the same route, so the facade opening and the crane standing area must still be there.
Generator overhaul via the installation shaft
In a larger building complex in the Rhine-Main region we removed and reinstalled the alternator of a standby generator for overhaul. A lift supervisor and three riggers dismantled the genset in the plant room and separated the alternator from the engine millimetre by millimetre with chain hoists. They set it on a made-to-measure timber transport frame and moved it on machine skates through the corridors to the installation shaft, where a mobile crane lifted it out. After the off-site overhaul it came back the same way, followed by reassembly and alignment. The job worked because the shaft existed and was clear, and the corridors allowed the load path – exactly the points in this guide.
CRAH unit replaced on the second floor
In a data center in Frankfurt we replaced a CRAH unit during live operation. The heat exchanger was damaged, its fin pack torn open down to the copper tubes. One supervisor and three riggers needed two working days. The new unit went from the lorry up to the second floor and was set in the narrow aisles of the CRAH gallery with two synchronised compact lifting devices. The old unit came out step by step, heavy modules such as the fan section on hydraulic machine skates. All routes were under protective fleece, access was through security gates with interlocked doors, and RAMS and lift plans were approved beforehand. The swap took two days partly because the load path to the second floor already existed. Our CRAH replacement checklist describes the sequence phase by phase.
Silencers retrofitted without a crane
In a live data center in Offenbach we installed twelve twin turbo silencers. They are intake silencers for the turbochargers of the standby generators, needed because only a street separates the generator rooms from neighbouring offices. No crane was available. The parts arrived by lorry, were unloaded in front of the building and taken to the floors by goods lift. Three fitters raised them with winch stackers onto base frames more than two metres above the generators, then aligned and bolted them. The connection is welded stainless steel pipework with flexible rubber connectors; acceptance included a performance test and a noise measurement at full load. For designers: retrofits will come, and space above the plant plus a goods-lift route make them possible.
Four jobs, one pattern: where route, space and isolation points existed, the replacement stayed within the window. Designing a data center now, or facing a replacement in a live building? Then get in touch with us. A site visit usually settles within an hour whether the replacement route works or where it needs improving.
What this means for your role
For buyers: Make replaceability part of procurement – as an award criterion for design services and as a line item in the installation scope of works. Require the contractor for the initial installation to hand over lift plans, load paths and weights as part of the documentation at acceptance, not as an extra. Record in the interface list what the client provides: crane standing area, opening, lift, isolation. At replacement time this saves a survey and gives you comparable quotations, because every bidder knows the same constraints – and nobody can claim a variation for an “unknown load path”.
For designers: Define a replacement route for each major unit and secure it in the structure, the external works plan and the operations plan: installation opening or shaft, lift capacity and door width, horizontal load path with swept path, crane standing area with ground bearing and radius, manoeuvring and laydown space. Plan openings and areas with reserve for the next generation of plant, and record imposed and point loads per section. Define service isolation per unit and document everything in the building file. Bring an installation contractor in early – a site visit at design stage costs less than a dismantling job in operation.
For project managers and site managers: When the replacement is due, the work starts with the building file and a site visit: what is documented, what must be re-surveyed, is the crane standing area clear, is a road-space permit needed? Make lift plan, RAMS and permit to work the precondition for lift approval, and plan maintenance, night or weekend windows in the programme with a fallback. How access, induction, protection, lifting equipment and documentation work in a data center is covered in the overview guide on data center installation. For generators, our services are listed under energy and standby power.
For maintenance managers: One day you will be responsible for the replacement – triggered by an inspection, remaining wear margin or obsolescence when parts are only available remanufactured. Check today that the replacement routes for your major plant are still clear and documented in the building file. Report changes of use of manoeuvring areas or crane standing areas before they become permanent. Agree with the operator which maintenance windows allow a replacement and how isolation and LOTO work for each unit. Bring the installation contractor in early, so that survey and lift plan are ready before the failure, not after it.
For facility managers and operators: Protect the planned areas and routes against change of use, and check with every change request for an extension whether the replacement route is still clear. Define in change control the remaining redundancy – N+1 or less – at which a replacement is allowed, which maintenance windows suit it and who issues the permit to work. Keep the building file current with lift plans, load paths and weights; at replacement time it is the basis for availability and audit.
Designer's replaceability checklist: template on request
The designer's replaceability checklist lists the checkpoints for concept and detailed design for each major unit – chiller, CRAH unit, generator, transformer, UPS: installation route (opening, shaft, lift, horizontal load path with dimensions), slab and floor loads along the route, crane standing areas with ground conditions and slewing area, manoeuvring and laydown space, service isolation per unit, redundancy during replacement, retrofit reserves and documentation for the building file.
Designers use it to work through replaceability systematically; operators use it to check during extensions whether the routes are still clear. The template is neutral and works for new build and existing buildings. Request it via our contact form – reference “replaceability”.
Why Omega Mounting?
Omega Mounting is based in Rodgau near Frankfurt, at the centre of the Rhine-Main data center market. The linked jobs cover exactly what you are designing for: new build, replacement and retrofit in live facilities – generator installation over three years, a generator overhaul via the installation shaft, a CRAH replacement in Frankfurt and a silencer retrofit in Offenbach. We bring this experience into the design stage with site survey, load path check and lift plan. Our workshop in Rodgau makes transport frames and load spreading plates to measure, and you can reach us by phone or WhatsApp when a replacement has to fit a short-notice maintenance window. In practice: one contractor from the load path check at design stage through lift and shift to maintenance of the standby generators – with short distances to Frankfurt, Offenbach, Hanau and Darmstadt, and documentation that is ready at the next replacement. If you want this experience in your design, get in touch with us.
Conclusion
Chiller replacement in a data center is not a question of if but when – as surely as the CRAH and generator replacements, in live operation, with a closed facade and reduced redundancy. Whether it takes two days or two weeks is decided at design stage. Keep the installation route, secure the crane standing area, keep the manoeuvring space clear, make services isolatable per unit, define the remaining reserve and document everything in the building file. That takes attention at design stage and saves downtime risk in operation. Send us the floor plan, component list with weights and your current design status – we will come back with an honest assessment of where the replacement route works and where it does not.
Planning a move-in, installation or maintenance in the Rhine-Main region?
Tell us briefly what you need – we'll come back with an honest assessment.
Free, no-obligation callback
You may also be interested in these guides
About the author
Tobias Schott
Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance
A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. He writes these guides from that practice: what works on our sites is in them – what exists only on paper is not.
Frequently asked questions
At least once in the building's life, because these units last far shorter than the data center – typically 15 to 20 years, depending on load and maintenance. Rising capacity needs or a phased-out refrigerant can bring the replacement forward.
Yes, if the remaining chillers carry the load – that is, if N+1 redundancy still holds with one unit out. The unit must also be individually isolatable, and a mobile crane must be able to reach the roof position. The operator sets the remaining reserve for a replacement in change control, and the swap is scheduled in a low-load maintenance window and kept short through full preparation.
An installation opening is an opening in the facade, roof or slab, closed in normal operation but removable, through which major plant is moved in and out by crane. Size it with reserve for the next generation of plant, including packaging and lifting equipment, not to today's unit. Behind it you need a laydown area with adequate slab loading.
Because conditions change: the facade is closed, the tower crane has gone, the crane standing area has a new use, the shaft may be blocked, space is occupied and diesel machines are banned inside. The operator's permit to work, induction and escort replace the GC's site rules. Only a route planned and protected as a replacement route will still be there when it is needed.
One from which a mobile crane with enough radius and hook height can reach every installation opening, shaft and roof position – on firm, documented ground with a known permitted ground pressure and a clear slewing area. Tandem lifts of very heavy units need two standing areas. The area belongs in the external works plan and must be protected against change of use; on a public road, every lift needs a road-space permit.
Only if the design allows for it. Temporary chillers or hire generators need external connection points and a standing area, and the designer should define them together with the remaining reserve at which a swap is allowed. Our part is to keep the time out of service short: the new unit waits ready on the laydown area, lift plan and protection are in place, and removal and installation follow straight on.
Load paths with permitted distributed and point loads; clear dimensions and capacities of openings, shafts and lifts; crane standing areas with ground data; manoeuvring and laydown areas; isolation valves and disconnection points per unit; and the lift plans, weights, lifting points, installation records and photos from the initial installation.
Because we can arrange a site visit or coordination meeting in Frankfurt, Offenbach, Raunheim or Darmstadt from Rodgau at short notice, and we know the region's data centers from new build, replacement and retrofit. That experience goes into the design before the first wall stands – and is there again when the replacement comes.
Yes. The documentation package from the initial installation includes a lift plan for every lift with load weights, lifting points, lifting accessories, machine positions and load paths. It also contains installation records with survey, alignment and torques, photos of the installation and notes on pinch points along the load path. These documents belong in the as-built file – years later they save a new survey when the unit is replaced.
Yes. We bring our experience from installation, replacement and retrofit into the design: site survey, load path check, crane standing area with radius and slewing area, and an outline lift plan. Designers and general contractors then see early whether installation openings, shafts, lifts and manoeuvring space will also work for the later replacement. A site visit at design stage costs less than a dismantling job in a live facility.