- Project report – Turbo silencers in Offenbach
Turbo silencers at a data center in Offenbach: 12 silencers against the whistling of the standby generators
How three fitters made an urban data center quieter – bringing in, installation and noise measurement under full load
A data center in the middle of the city – only a street separates the generator rooms from an old industrial building full of offices. When the standby generators run under full load, the turbochargers whistle so loudly that the neighbourhood cannot accept it. The solution: turbo silencers. At a data center in Offenbach am Main, Omega Mounting brought in 12 twin turbo silencers and distributed them to the floors via the goods lifts. We installed them on purpose-built base frames above the generators, together with intake filters, welded stainless steel pipework and a final noise measurement under full load.
Project profile
- Scope: Bringing in and installing 12 twin turbo silencers, incl. base frames (over 2 m high), intake filters and welded stainless steel pipework with flexible rubber connectors – plus performance test and noise measurement under full load
- Team: 3 fitters from Omega Mounting
- Duration: Several construction phases, spread over several weeks
- Location: Data center in Offenbach am Main
What is a turbo silencer?
A turbo silencer is a silencer for the intake side of the turbocharger on large diesel engines. Under load, turbochargers produce a characteristic high-frequency whistle – hardly an issue with a single lorry, but a considerable source of noise with several standby generators in the megawatt range. The turbo silencer sits between the intake filter and the turbocharger and absorbs exactly these frequencies without throttling the airflow the engine needs for full output. For data centers in urban locations, silencers like these are often the prerequisite for operating the standby power system in compliance with its permit at all.
Why did this data center need turbo silencers?
Because it was built in the middle of the city. Only a street separates the generator rooms from an adjacent old industrial building that now houses offices. During full-load tests of the standby generators, the whistling of the turbochargers was clearly audible – not acceptable in the long run for the neighbourhood or the noise control requirements. So a solution was needed: turbo silencers on every generator, retrofitted into a finished building that was already in operation. It is exactly this combination – tight space, live operation, heavy material – that is classic Omega Mounting work.
How do you get 12 twin turbo silencers into a finished data center?
Via the goods lifts – and with a lot of planning. The silencers arrived by lorry, were unloaded in front of the building, taken up in the goods lifts and distributed to the individual floors. There was no crane in the generator rooms, so we worked with winch stackers. First, a base frame was fitted over each generator – just over 2 metres high, because the silencers sit above the generator. We then lifted the large silencers onto the frames with the winch stackers, aligned them and bolted them down. Large intake filters were fitted to the silencers as well.
How are the silencers connected to the turbochargers?
Via specially welded stainless steel pipes and flexible rubber connectors. The pipework ensures that the airflow fits exactly and the engine receives the full volume of air under full load. The rubber connectors perform a second, decisive task: they mechanically decouple the turbochargers from the silencers. A generator of this size produces considerable vibration under full load – if silencer and turbocharger were rigidly connected, the vibration would pass straight into the structure. That is why the entire installation was bolted and secured so that even strong vibration under full load causes no problems.
How do you check whether the silencers work?
With a performance test and noise measurement under full load. At the end of the installation, the generators were run up and measured under full load – inside and outside. In the generator room itself it remains very loud even with hearing protection; that is unavoidable. What matters is the outdoor area: there, the installation has shown its effect audibly – or rather, no longer audibly. The whistling of the turbochargers has disappeared from the neighbourhood, and the generators can run their full-load tests without anyone looking up in the office across the street.
Data centers, generators, standby power systems: our core business
This job joins a long list: our crews work on international data center projects every day. Around generators and standby power systems, we have carried out emergency radiator repairs and lifted generators through installation shafts by mobile crane for maintenance. We have also brought in load banks for load tests, replaced CRAH units and installed PDCs in a multi-hall rollout. We know the safety and approval processes in data centers, the tight installation routes and the requirements for working next to live critical infrastructure.
Why Omega Mounting?
- Data center routine, not the exception: We work in data centers every day and know access rules, safety processes and commissioning procedures inside out.
- Generator and standby power experience: From crane lift-outs and load bank logistics to emergency radiator repairs – standby power technology is one of our core topics.
- Installation without a crane: Goods lifts, winch stackers, tight rooms – we bring heavy material even to where no crane can reach.
- Installation down to the last detail: Base frames, pipework, vibration decoupling, bolting – we deliver the complete mechanical installation from one contractor.
- Measurable results: For us, a performance test and noise measurement under full load are part of the acceptance.
- Rooted in the region: From Rodgau, we are quickly on site in Offenbach, Frankfurt and the entire Rhine-Main region.
Conclusion
12 twin turbo silencers, 3 fitters, several construction phases – and a data center whose standby generators can now run under full load without disturbing the neighbourhood. Retrofitting noise control to standby power systems is precision work: moving heavy components into finished buildings, installing them to the millimetre above the generators and connecting them with vibration decoupling. If your site has a similar noise or installation problem, get in touch.
Request a callback – Omega Mounting GmbH, Rodgau. We work in the Rhine-Main region and throughout Germany.
How the generator, exhaust line and peripherals get into place in the first place is described in the overview article Standby generator installation in data centers.
More projects in Offenbach: Industrial installation in Offenbach (German).
Project photos
Planning a similar project?
Tell us briefly what you need – we'll come back with an honest assessment.
Free, no-obligation callback
Related guides for this project
About the author
Tobias Schott
Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance
A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. The project diary shows jobs his team has planned and carried out – without client names, but with everything there is to learn from them.
Frequently asked questions
The high-frequency whistling is caused by the fast-rotating compressor wheels of the turbocharger on the intake side. With large generators in full-load operation, this noise becomes so loud that it becomes a problem for the neighbourhood and noise control in an urban environment.
It specifically attenuates the high-frequency intake noise of the turbocharger without throttling the airflow. The generator retains its full output, and the whistling in the outdoor area disappears – audibly confirmed on this project by noise measurements under full load.
Yes. On this project, all 12 twin turbo silencers were retrofitted: delivered by lorry, distributed to the floors via the goods lifts and lifted with winch stackers onto base frames over 2 m high above the generators – without a crane.
For vibration decoupling. Generators produce strong vibration under full load. The flexible rubber connectors between the stainless steel pipework and the turbocharger stop this vibration from passing into the silencer structure and causing damage there.
So loud that it remains very loud even with hearing protection – which is why hearing protection is mandatory there and exposure time is kept short. What matters for the surroundings, however, is the outdoor noise level, and that is exactly what the turbo silencers reduce considerably.
Yes, regularly. Our crews work in data centers in the Rhine-Main region every day, for example in Offenbach and Frankfurt. They know the safety, access and approval processes for working next to live critical infrastructure.
In a power failure, the standby generators take over the supply of the data halls within seconds. So that they can be tested and run at any time, noise control requirements must also be met – otherwise test runs may be restricted.
Yes, that is how this job ran. The twelve twin turbo silencers arrived by lorry, were unloaded in front of the building and distributed to the floors via the goods lifts. There was no crane in the generator rooms, so we worked with winch stackers. First came the base frames, just over 2 metres high; then we lifted the silencers onto them, aligned them and bolted them down.