Load spreading mats: why the ground decides more than the crane

By Tobias Schott  · 7-minute read · Updated October 2026

Packed and levelled skidding system above the pit of the transformer cell
Packing under every bearing point: where around 52 tonnes rest on a few points, the ground beneath decides.

Load spreading mats spread the force of an outrigger, a skate or a bearing point over a larger area – and so decide whether the ground carries a heavy lift or gives way.

Load spreading mats sit under the outriggers of every mobile crane, under MEWPs and on the routes of heavy transports. On site they are called outrigger pads, crane mats, spreader plates or simply “the mats”; the German terms are Lastverteilplatten or Abstützplatten. If you treat them as an accessory, you underestimate them: the crane’s capacity is no use if the ground under one outrigger collapses.

This article explains what ground bearing pressure is, which types of mat exist and where the typical mistakes lie. How to plan floor loads and crane standing areas for your project is covered in our move-in planning guide – we do not repeat it here.

What is a load spreading mat?

A load spreading mat is a stiff plate of steel, aluminium, plastic or timber that spreads a concentrated force over a larger area and so reduces the pressure on the ground. It sits between equipment and ground: under a crane’s outrigger foot, under the wheel of a heavy-duty skate, under the bearing of a skid track.

A point load – a force acting on a very small area – becomes a distributed load. The mat does not make the ground any stronger. It only spreads the load so that the existing ground can take it. Whether that is enough depends on the ratio of force, area and permissible ground bearing pressure.

Key facts

Ground bearing pressure: force divided by area

Diagram: ground bearing pressure with and without load spreading mats – force divided by area, outrigger foot compared with mat in a fictitious example
Same force, sixteen times the area, one sixteenth of the pressure – provided the mat is stiff enough. Fictitious example. Graphic: Omega Mounting

Ground bearing pressure is the force pressing on the ground divided by the area it rests on – the same force on twice the area means half the pressure. The unit is kilonewtons per square metre (kN/m²). On site, people often calculate in tonnes per square metre. One tonne of mass presses on the ground with around ten kilonewtons.

A fictitious example with round numbers: an outrigger presses with 20 tonnes on a foot of 50 by 50 centimetres, i.e. 0.25 square metres. That gives 80 tonnes per square metre. A stiff mat of 2 by 2 metres spreads the same force over 4 square metres – 5 tonnes per square metre. The area grows sixteenfold and the pressure drops to one sixteenth.

The calculation only holds if the mat is stiff enough. A mat that is too thin bends under the foot, and the pressure stays concentrated in the middle. With a load spreading mat, area and stiffness count together.

The permissible ground bearing pressure depends on the ground. The values come from the structural engineer or the geotechnical engineer; we take them over, we do not estimate them. Who sets and approves them is governed by the design and the contract – this is not legal advice but the division of work on site. In qualitative terms, the grounds differ like this:

Where does the force on the mat come from?

The force on a load spreading mat comes from the equipment above it – and it is rarely spread evenly. On a mobile crane, the load moves from outrigger to outrigger as the crane slews. The outrigger on the load side carries a large share of crane weight, counterweight and load. The crane hire company provides the outrigger forces for the planned lift from its lift planning; they are the basis for every mat size.

Technische Zeichnung: Mobilkran in Draufsicht mit vier Stützen auf Lastverteilplatten, Kraft je Stütze als Kreis, größte Kraft auf der Lastseite, Schwenkbereich
Die Stütze auf der Lastseite trägt am meisten – schwenkt der Kran, wandert die Kraft zur nächsten Stütze. Grafik: Omega Mounting
Timber baulks take the load and protect the platform of the site hoist
Timber baulk packing under a construction hoist and ramp: the timbers take the load so that the platform does not bend.

Which load spreading mats are there – and what does each one carry?

Load spreading mats differ mainly in stiffness, self-weight and handling – and therefore in which force they can bring onto which area. The rule of thumb: the higher the outrigger force and the softer the ground, the larger and stiffer the mat has to be.

Technische Zeichnung: sechs Lastverteilplatten im Schnitt – Stahlplatte, Aluminiumplatte, Kunststoffplatte, Holzmatte, Kantholz-Unterbau und Bodenschutzplatte mit Lastausbreitung im Boden
Je steifer und größer die Platte, desto breiter verteilt sie die Kraft – eine Bodenschutzplatte verteilt kaum. Grafik: Omega Mounting
Mat typeMaterialStrengthLimitTypical use
Steel plateStructural steel, smooth or chequeredVery stiff, spreads high forces even over large areasHeavy, can only be laid with equipment; slippery when wetCrane outriggers on soft ground, bridging joints and channels
Aluminium outrigger padAluminium, often with handlesLighter than steel with good stiffnessNotches and dents at the edges weaken itOutriggers of mobile and mini cranes
Plastic padSolid polyethyleneLight, slip-resistant, does not absorb waterLess stiff than metal, needs thickness and area; heat deforms itMEWPs, mini cranes, routes for skates
Timber mat (crane mat)Joined planks or timber baulksLarge area, signals overload by indentationHeavy, absorbs water, splits and rots over timeLarge cranes on unpaved ground
Timber baulk packingStacked timber baulks, laid crosswiseHeight and area freely adjustableOnly as good as the stack and its bearing; tips if laid at an angleSet-down points, temporary support of components, packing under tracks
Floor protection boardThin plastic, often with fleeceProtects surfaces from scratches and dirtBarely spreads load – not a load spreading mat in the true senseRoutes through finished halls

The last row is the most important distinction: a protection board protects the floor from the equipment, a load spreading mat protects the equipment from the ground. On sensitive industrial floors you therefore often find both, one on top of the other.

When is the mat no use?

A load spreading mat is no use if there is no load-bearing ground beneath it or if it does not pass the force on evenly. These are the mistakes we see most often:

Technische Zeichnung: vier Fehler bei Lastverteilplatten im Schnitt – Kanal unter der Platte, Platte zu nah an der Grubenkante, durchgebogene Platte, außermittiger Teller auf Gefälle
Hohlraum, Grubenkante, zu dünne Platte, schiefe Lage: Dann kommt die Kraft nicht dort an, wo der Boden sie tragen kann. Grafik: Omega Mounting

What we pay attention to

Our fitters treat the ground under the equipment as part of the lift, not as a given.

Where we use it

In the Rhine-Main region, the ground has a say in almost every heavy lift. When moving two transformers in on a skid track around 52 tonnes each rested on just a few bearing points. The track was packed, measured and adjusted element by element before the push; the lift management checked the crane position against the ground loading in advance. When five diesel tanks were installed in Raunheim, there were shafts, ducts and basement light wells under the access routes that cannot take point loads from crane outriggers – only after surveying the existing conditions was it clear where the crane could stand. We clarify questions like these as part of Lift & Shift before the first lift.

Two diesel tanks set down in the pit, with the area of the crane position behind them
Temporary crane standing area: the ground – and what lies beneath it – decides where the crane may stand.

More technology explained

Technology explained

The track whose bearings must stand on load-bearing packing.

Technology explained

Why with skates the ground is the limit, not the capacity.

Guide

The guide for when you set floor loads and crane standing areas for your project.

Do you have questions about how this works on your site?

Questions about how this works on your site – whether the crane standing area will carry the load, which mats belong under the outriggers or how a route crosses the hall floor? We look at ground, equipment and route together with you. Request a callback – we will get back to you.

Free, no-obligation callback

Tobias Schott, managing director of Omega Mounting GmbH, on a construction site in front of scaffolding

About the author

Tobias Schott

Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance

A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. The Technology explained articles cover the equipment and techniques his team uses every day: what counts on site is in them – what only appears in the brochure is not.