The skidding system: when the transformer does not fit through the gate

By Tobias Schott  · 8-minute read · Updated October 2026

Hydraulic skidding system running from the building entrance into the transformer cell
A skidding system replaces the crane on the last few metres: from the building entrance across the pit and into the transformer cell.

A skidding system pushes loads of many tonnes horizontally over steel rails to where no crane hook can reach any more – and thus decides whether a transformer gets into its finished building at all. You usually only come across the skidding system once the crane has reached its limit. The building is closed, the roof opening long since sealed, the transformer is standing on the low-loader outside the door. The crane brings the load up to the opening – through the gate and into the transformer cell it has to continue at floor level. That is exactly what a skidding system is laid for.

In data centers, substations and machine halls this is a standard case: the building comes early, the heaviest plant comes late. Here we explain what a skidding system is, how it is constructed, how a skidding operation proceeds and when we prefer it to skates or a crane.

What is a skidding system?

A skidding system is a rail or slide track of steel elements laid on the floor. Hydraulic cylinders or a winch push a heavy load along it horizontally to its installation position. The method is called skidding – in the UK usually jacking and skidding – and the track a skid track. The load does not roll; it slides: between load and rail sit skid shoes with a low-friction sliding pair. As a result, a pushing force amounting to only a fraction of the load weight is sufficient.

The skidding system is part of the toolkit of Lift & Shift. It is not a permanent installation like an overhead crane but is laid, operated and dismantled again for a single job.

Key facts

Elements of the skidding system with hydraulic cylinder before the transformer is skidded in
Rail, skid shoe and push cylinder – every element of the track consists of these three parts.

How is a skidding system constructed?

A skidding system consists of rail elements, skid shoes, push cylinders, a hydraulic power unit and the packing:

Technical drawing of a skidding track in cross-section and side view: load with centred centre of gravity on two parallel rail tracks, skid shoes with sliding pads, rail elements with teeth on cribbing and load spreader plates, and a skidding cylinder whose claw grips the teeth
Two parallel rail tracks carry the load on skid shoes – the skidding cylinder grips the teeth of the rail and pushes the load forward. Graphic: Omega Mounting

Two track strands run in parallel under the load, spaced at the support points. If the floor is missing at one point – for example over a transformer pit – the track spans the gap as a girder.

How does a skidding operation proceed?

Explanatory graphic: sequence of a skidding operation on the skid track in four phases – lay and level, set down, push stroke by stroke, set down on the foundation
Four phases, one principle: the load stands still after every stroke and is checked before the next one follows. Graphic: Omega Mounting

A skidding operation proceeds in four phases: lay and level the track, set the load down on it, push stroke by stroke, set down on the foundation. The first phase is the longest.

Technical drawing of one skidding stroke in three panels: the claw grips the teeth of the rail, the cylinder pushes the load one stroke length, then retracts and grips again, with a pressure gauge for checking the force in the pause
After every stroke the load stands still – pressure, position and alignment are checked before the cylinder grips again. Graphic: Omega Mounting

Because of these pauses, a skidding operation over a few metres often takes longer than the crane lift before it. The slow pace is not a shortcoming but the safety principle of the method.

Where does the load go – slab load and load distribution?

The load does not go into the floor over an area but at points via the supports of the track. The path is always the same: skid shoe, rail, packing, floor. At each support, part of the load weight acts as a point load.

With a ground-bearing slab this is rarely a problem. On a suspended floor it is different: slabs are designed for distributed loads, but a skidding system introduces point loads. Load spreading plates and additional steel girders distribute them over several slab bays or carry them to the column lines. Which slab carries which load belongs in the installation planning – the guide on slab loads, openings and crane standing areas explains what the planner has to provide.

Technical drawing comparing a skidding track resting directly on a floor slab in mid-span, where the point loads make the slab deflect, with steel beams that carry the load to the column lines
Floor slabs are designed for distributed load – steel beams take the point loads of the skidding track to the column lines. Graphic: Omega Mounting

Raised floors in data halls are a special case: they carry cabinets but not a skidding system. There, the raised floor is opened or the load is transferred via steel plates down to the structural slab. Where the track spans a pit, we check the pit edges separately – that is where the support force is concentrated on a few points.

Skidding system, machine skates or crane: when which method?

The skidding system is the method for the heaviest load on the most difficult route – everywhere else there are faster ways:

MethodStrengthLimitTypical case
skidding systemCarries very heavy loads, guides them precisely, bridges pits and edges, needs no hook height.Set-up and levelling time, space for track and cylinders, ground must carry the supports.Transformer or generator into a closed cell
Machine skatesFast, manoeuvrable, curves and changes of direction without reconfiguration.Floor covering and ground pressure, thresholds and gradients, high centre of gravity.Machine tool through the hall on a level industrial floor.
Hydraulic gantryLifts loads weighing tonnes without a crane runway, repositions them.Lifting and short distance only, needs space around the load.Press from the transport frame onto the foundation.
Mobile craneFast over great height and distance, one lift instead of many strokes.Needs an opening from above, set-up area and free hook height.Shell building without roof, plant is lifted in from above.

In practice we combine the methods: the crane brings the load to the opening, the track takes over the last few metres, hydraulic jacks set it down. We choose skates when load and floor allow it – then the track is simply too elaborate. What drives the effort is not the metres but differences in height, lack of space for the packing and waiting time for crane and low-loader.

What we pay attention to

In skidding, preparation decides the day. We check this before the load goes onto the track:

Technical drawing of Skidding track with numbered check points: Levelling, Direction of push, Cylinder anchored, Watch the pressure, Set-down points, Exclusion zone
Track levelled, cylinder anchored, pressure watched, set-down points ready, area clear. Graphic: Omega Mounting

Where we use it

We use the skidding system where the load is too heavy for skates and the building too enclosed for the crane. In a data center in the Frankfurt area, two fitters and a lift supervisor skidded two transformers of around 52 tonnes into their cells in one working day. They went straight from the low-loader onto the track, with just over an hour of pure skidding time each. Set-down was on stacked timber baulks in the transformer pit – read about it in the report on two transformers on the skidding system. The track there was provided by the client; our team packed it, levelled it and operated it. The counter-example shows when no track is needed: for the roll-out of 160 power distribution cabinets across four levels, a heavy-duty lift, a lifting gantry and a hall floor under protective plates and fleece were sufficient. How we bring heavy plant from the lorry to the foundation is described on our page Lift & Shift.

More technology explained

Technology explained

The faster alternative when load and floor allow it.

Technology explained

The lifting device that raises the load before and after skidding.

Guide

The guide for planners, so that the track later finds a route and a load-bearing floor.

Do you need this machine together with a team on site?

Do you need a skidding system together with a team that lays it, levels it and brings the load safely into the cell? We plan the route from the low-loader to the foundation and run the skidding operation. The quickest route: callback – briefly describe your load, building and date.

Free, no-obligation callback

Tobias Schott, managing director of Omega Mounting GmbH, on a construction site in front of scaffolding

About the author

Tobias Schott

Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance

A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. The Technology explained articles cover the equipment and techniques his team uses every day: what counts on site is in them – what only appears in the brochure is not.

Frequently asked questions

We do not bring our own skidding system: it is provided by the client, the haulier or a specialist partner. We lay, pack and level the track and operate the system on site; our appointed person (AP) plans the move. On the job near Frankfurt the client provided the track, and we laid, levelled and operated it.

There is no single figure – the limit is set by the system and above all by the floor. Depending on the system, skidding systems typically move from several tens to several hundred tonnes; what decides is the slab load at each support, the pit edges and the space for packing. Our documented reference is two transformers of around 52 tonnes each, skidded into a data center near Frankfurt in one day.

A pit, yes: where the floor is missing, the track spans the gap as a girder. We check the pit edges separately, because that is where the support force is concentrated on a few points. Raised floors in data halls are different – they carry cabinets but not a skidding system. There, the raised floor is opened or the load is transferred via steel plates down to the structural slab.

EnglishEnglish