The lift plan: what goes into a lifting plan – and why no hook goes up without one

By Tobias Schott  · 5-minute read · Updated November 2026

Tandem lift with two cranes: containerised standby power system above the building
A tandem lift with two cranes – every crane, every load and every movement was in the lift plan beforehand.

A lift plan – also called a lifting plan – is the document that fully describes a lift before it takes place: which load, which crane, which lifting accessories, which crane position, which sequence and who approves it.

On data center sites and large industrial projects, the phrase comes up again and again: no lifting without an approved lift plan. This is not a formality. In the lift plan, every lift is run through once on paper so that nothing comes as a surprise on the day – not the weight, not the ground and not the neighbouring building.

Here we explain what goes into a lift plan, what the side view and top view show and how the plan goes through to approval. How to plan a crane lift step by step is described in our guide Planning a crane lift.

What is a lift plan?

A lift plan is the written planning of a lift with all the information needed to carry it out safely and have it checked beforehand. Other names are lifting plan, rigging plan or crane plan; in German it is called Liftplan or Hubplan.

Not every lift needs the same effort. A routine lift with a known load and a clear crane position needs only a short plan. A tandem lift, a lift over a building or a lift next to live operations needs a detailed plan with calculations and drawings. The more that can go wrong, the more precisely it is planned.

A lift plan usually consists of a form with the data, a side view and a top view. It is prepared by the person responsible for the lifting operation. On large sites it is checked and approved by the main contractor or operator – often digitally in their management system.

Key facts

What goes into a lift plan?

Technical drawing of a lift plan sheet with fields for load data, crane and configuration, lifting accessories, top view of the crane position, sequence and signatures
Load, crane, rigging, crane position, sequence and approval – six blocks that every lift plan must answer. Graphic: Omega Mounting

A complete lift plan answers six questions.

BlockWhat it contains
LoadWeight, dimensions, centre of gravity, lifting points, condition.
CraneType and configuration, counterweight, boom length, radius, capacity and utilisation at the target point.
RiggingLifting accessories as specified by the manufacturer, rigging geometry, angle of inclination, spreader beam.
Crane positionOutrigger forces, ground pressure, load spreading mats, manholes and services in the ground.
Surroundings and sequenceObstacles, slewing area, barriers, wind limit, sequence of movements.
People and approvalResponsible person, crane operator, slinger, banksman, communication, signatures.

Most of the work goes into the load assumptions and the crane position. The weight must be documented, not estimated. And the forces under the outriggers must be checked against what the ground can carry.

The side view: radius, height, outriggers

Technical drawing of a mobile crane on outriggers with a load on the hook, dimension arrows for radius and lift height over a building, counterweight and load spreading mats under the outriggers
The side view shows what the crane must achieve – radius, lift height over obstacles and the outriggers on the ground. Graphic: Omega Mounting

The side view shows the lift as the crane sees it.

How radius and capacity are related is explained in our article on load moment and radius.

The top view: crane position and danger zone

Technical drawing in top view with crane position, slewing area, cordoned-off danger zone, delivery vehicle, set-down point at the building and a manhole that must not be loaded
The top view shows crane position, slewing area, barriers, delivery and set-down point – and what in the ground must not be loaded. Graphic: Omega Mounting

The top view shows where everything stands and where the crane slews.

What the outriggers stand on and how mats reduce ground pressure is covered in our article on Load spreading mats.

From draft to approval

Technical drawing in four steps: the lift plan is prepared, checked and approved, the team is briefed at the crane, the load is lifted
Plan, get approval, brief, lift – only when all steps are done does the load go on the hook. Graphic: Omega Mounting

A lift plan is only finished once it has been approved.

If anything changes – different weight, different crane position, different crane – the plan is adjusted and approved again. Who bears the responsibility is explained in our guide on the appointed person for lifting operations.

Typical gaps in a lift plan

Most problems in a lift arise not at the crane but in the plan. These gaps keep coming up:

A lift plan applies to exactly the lift described. If the crane position, crane, weight or slinging method changes on site, the plan is adapted and approved again – even if it costs time. A lift carried out to an outdated plan is a lift without a plan.

What we pay attention to

A lift plan is only as good as the data in it.

Where we use it

During the installation of standby generators in data centers every lift is pre-planned in the lift plan – load assumptions, rigging geometry, crane set-up, radius, ground pressure and the sequence of movements. For a tandem lift with two mobile cranes, the plan also states how the load is distributed. If one crane lags behind, this distribution is no longer correct.

During the replacement of a CRAH unit in a live data center we prepared the RAMS and lift plans ourselves before a supervisor and three riggers took the unit out and brought the new one in.

More technology explained

Do you have questions about how this works on your site?

Do you need a lift plan that gets through with the main contractor – or a responsible person for the whole lift? We plan, get approval and lift. Request a callback.

Our service for this: Lift & shift: rigging and lifting →

Free, no-obligation callback

Tobias Schott, managing director of Omega Mounting GmbH, on a construction site in front of scaffolding

About the author

Tobias Schott

Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance

A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. The Technology explained articles cover the equipment and techniques his team uses every day: what counts on site is in them – what only appears in the brochure is not.

EnglishEnglish