- Technology explained – machines and equipment
Mobile crane, crawler crane, all-terrain crane: which crane does what – and what it does not
By Tobias Schott · 8-minute read · Updated October 2026
A mobile crane drives to site on its own axles, sets up on outriggers and leaves after the lift. Its limit is rarely its capacity – it is the radius and the ground it stands on.
Mobile cranes appear in every tender where something heavy has to go over a facade, down a shaft or onto a roof. Terms such as all-terrain crane, crawler crane and loader crane are often mixed up. Once you separate them, it becomes clear why a crane hire company sends a machine rated at several hundred tonnes for a 16-tonne load.
We do not operate mobile cranes – they come with the hire company's operator; only our own spider cranes are operated by our team. We plan and lead the lift, sling the load and give the signals. That is why we need to know what each crane type can do and where it stops.
What is a mobile crane?
A mobile crane in the narrow sense is a crane with a telescopic boom on a road-going chassis that transfers its load into the ground through extended outriggers. Depending on design it is called an all-terrain crane or a truck crane (crane on a lorry chassis). In the broad sense, mobile crane is the umbrella term for every crane that moves under its own power – including crawler cranes and mini cranes. On site, “mobile crane” usually means the all-terrain crane.
Key facts
- Type: Telescopic boom on a multi-axle chassis, slewing superstructure, four extendable outriggers
- Typical capacity: from a few dozen to well over 1,000 tonnes rated capacity – available only at the shortest radius
- Drive: Diesel engine for travel and crane work; large machines have separate engines for carrier and superstructure
- Field of use: Lifting plant over facades and into shafts, installing plant on roofs, setting tanks and containers, erecting other cranes at height
- Requirements: firm, level crane standing area, clear access, outriggers on load spreading mats, distance from overhead lines, wind limit observed
- Operator qualification: Crane operator supplied by the crane hire company, trained and authorised in writing under the German crane regulation (DGUV Regulation 52); a named person is responsible for the lifting operation
Mobile crane, all-terrain crane, crawler crane, loader crane: how do they relate?
Mobile crane is the umbrella term; all-terrain, crawler, loader and mini cranes are the types beneath it, and each does one job better than the others. The all-terrain crane is the all-rounder: quick to arrive, quick to rig and enough for most industrial lifts. The crawler crane carries more, stands on its tracks without outriggers and can travel with a load. It needs low-loaders, an erection area and several days to rig. Its lattice boom is lighter than a telescopic boom, which gives it the edge at great heights and long radii.
The loader crane sits behind the cab of a lorry and lifts what that lorry brings; its limit is its small load moment, given in tonne-metres. The mini crane – most often a spider crane – is the only type that drives through a door into the building.
| Type | Field of use | Strength | Limit | Preparation |
|---|---|---|---|---|
| Mobile crane | Outdoor lifts over facades, into shafts and onto roofs; work at great height | Drives to site, rigs in hours, wide range of capacities | Needs a level, firm standing area and room for the outriggers | Confirm crane standing area, access, ground bearing assessment, overhead lines |
| Crawler crane | Very heavy loads, long hire periods, lifts with travel under load | Highest capacity, travels with load, needs no outriggers | Delivered in parts, needs an erection area and days to rig | Low-loader logistics, erection area, travel path for the tracks |
| Loader crane | Loading and unloading lorries, small installation lifts straight from the vehicle | Transport and lift with one vehicle, no second machine | Small load moment, low lifting height, short radius | Space for the lorry, outriggers, known load weight |
| Mini crane | Interiors, basements, halls without an overhead crane | Fits through standard doors, electric drive available | A few hundred kilograms to a few tonnes, small outrigger footprint | Check slab loading, door widths, outrigger positions |
How does a crane carry the load? Load moment, radius, counterweight
A crane does not carry a load according to its rated capacity but according to the load moment: load weight multiplied by radius, the horizontal distance from the slewing centre to the hook. As a rule of thumb, double the radius and you halve the permitted load. In practice it drops even further, because the boom's own weight counts too. Any capacity figure without a radius is therefore meaningless.
What the crane may lift at each radius and boom length is set out in the manufacturer's load chart. The chart applies only to the actual configuration: counterweight on the superstructure, outrigger base, boom length and any fly jib. The counterweight balances the tipping moment of the load; without the right counterweight, no line of the chart is valid. The rated capacity indicator (load moment limiter) stops the movement before the crane tips – but it does not replace planning.
The outriggers carry the forces into the ground. Each of the four outriggers can see many tonnes, depending on crane and load. Load spreading mats increase the contact area and reduce the ground pressure, the force per square metre. Whether the ground can take it depends not on the surface but on what lies beneath: shafts, ducts, basement slabs, backfilled pits.
An example from our own work: to lift a standby power system onto the second floor, about 16 metres up, two mobile cranes rated at 650 tonnes each were set up. That figure says less about the weight of the load than about the radius the cranes had to work at.
What is a tandem lift?
A tandem lift is a lift in which two cranes carry the same load at the same time because it is too heavy, too long or too bulky for one crane. The classic case is a long container that must stay level and whose lifting points are far apart.
A tandem lift is more than two single lifts side by side. The load splits unequally between the hooks according to its centre of gravity, and any tilt shifts that split. That is why we add a load-sharing allowance to each crane's share and keep both hoist ropes vertical throughout the lift. Both cranes move only on command, and exactly one person gives that command.
The lift plan sets out which crane carries which share, in which order the load is raised, slewed and set down, and where it can be landed if the lift is aborted. What the plan contains and who approves it is explained in our guide on the appointed person for lifting operations.
What must the client prepare before the crane arrives?
Before the crane arrives, the client must sort out four things: the crane standing area, the access, overhead lines and the weather. Each of them decides whether the crane ordered can work at all.
- Crane standing area. It must be level, large enough and able to carry the load right down into the subsoil. A ground bearing assessment shows what outrigger loads the area can take; shafts and ducts beneath it are the most common surprise.
- Access. All-wheel steering makes a mobile crane manoeuvrable, but it is long. Turning circles, gates and barriers are measured, and escort vehicles and counterweight lorries are included.
- Overhead lines. Live overhead lines require safety distances of one to five metres depending on voltage; if the voltage is unknown, the largest distance applies. Otherwise the line is switched off or fenced off.
- Wind limit. The load chart only applies up to the wind speed stated in the operating manual – what counts is always the manufacturer's figure for the crane in use, not a general rule of thumb. Large surfaces such as containers lower that limit considerably.
We also agree the split of duties in writing beforehand. The crane hire company supplies crane, operator and counterweight and stays responsible for operating the machine safely. We plan the lift, select lifting accessories and lifting points, sling the load, give the signals and approve every lift. UK readers: under BS 7121-1 the appointed person (AP) plans the lift and a lift supervisor runs it on site; the split described here is our practice in Germany, not legal advice.
What we pay attention to
On every crane job we check the same points, because that is where mistakes cluster.
- We ask about the standing area first, then about the crane. The right machine is the one that just reaches from the permitted area. More capacity also means more weight, larger outrigger loads and more space for rigging.
- We read the load chart for the actual configuration. Counterweight, outrigger base and boom length on site must match the chart line the lift needs. Anything else is a calculation error.
- We calculate the load weight including lifting accessories, spreader beam and hook block. On a tandem lift we add the allowance for unequal load sharing.
- We protect the standing area against changes. Ground that carries the crane today may not carry it tomorrow if someone digs next to it.
- We check the lifting points before the hook arrives. A visual check and a recalculation of the geometry are part of approving the lift, even when the load's manufacturer has specified the points.
- We stop the lift when an assumption no longer holds. Wind, visibility, a vehicle in the slewing area: the approval only covers the situation that was planned.
Where we use it
In the Rhine-Main region, mobile cranes are part of almost every lift and shift job we do – lifting and relocating heavy plant. During the tandem lift of a standby power system onto the second floor, two mobile cranes rated at 650 tonnes each lifted a container unit over the facade; the heaviest containerised unit we have installed so far weighed 54 tonnes. When five diesel tanks were set into a pit in Raunheim, the standing area decided the machine: the crane with a 52-metre main boom and up to 44 metres radius fitted in only a few positions, and the site gates had to be taken down. What we provide on such jobs is described on our page on Lift & Shift.
More technology explained
Technology explained
the smallest crane type, for when no mobile crane can get in.
Technology explained
the fixed crane that a mobile crane often installs in the first place.
Guide
how designers fix standing areas and access routes at the design stage.
Do you need this machine together with a team on site?
Need a crane lift with planning, slinging and signalling from one contractor? We agree crane, standing area and lift plan with the crane hire company and lead the lift on your site. Request a callback – we will come and look at your site.
Free, no-obligation callback
About the author
Tobias Schott
Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance
A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. The Technology explained articles cover the equipment and techniques his team uses every day: what counts on site is in them – what only appears in the brochure is not.
Frequently asked questions
The client provides a crane standing area that can carry the load and backs it with a ground bearing assessment. Outrigger loads depend on the crane, its configuration and the load. In the lift plan we fix the crane position and outrigger arrangement and check them against that assessment. Shafts, ducts and basement slabs beneath the area are the most common surprise, so we ask about the standing area first and the crane second.
Allow about one week before the lift. In that time our appointed person (AP) checks the load data and lifting points, agrees the crane position and the crane with the crane hire company, and sets out the lifting accessories and exclusion zone in the lift plan. Missing information on the load or the ground is settled at a site visit.
Yes. We plan tandem lifts with the load split according to the centre of gravity, an allowance on each crane’s share and a landing position in case the lift is aborted. On site, exactly one person gives the commands for both cranes. One example: a standby power system lifted onto the second floor by two mobile cranes rated at 650 tonnes each. Cranes and operators come from the crane hire company.
As standard, we hire the mobile crane with its operator (crane hire, in the UK often called CPA hire); a contract lift is not our standard. Our appointed person (AP) and our engineering team plan and lead the lift, and our own riggers, slingers and banksmen/signallers carry it out on site. The lift plan states who is responsible for what.