Partitioning a battery test station with dividing walls
Project diary
Several dividing walls erected in a battery test station: electrically shielded partitions with safety doors, installed in one day by a team of four.
We were called in as the installation contractor. Our task was to install partition walls that electrically shield the compartments from each other, so that every station is protected on its own during battery testing.
Project profile
- Client sector: Battery testing in a production plant
- Scope: Electrically shielding dividing walls with earthed safety doors, contact switches and electric locks – installed as subcontractor
- Team: 4 fitters
- Duration: 1 day, during live production
- Result: The client could install its test station shortly afterwards



Overview
- 22 January 2024
- Erecting dividing walls
- Battery test station
- Safety requirements
- One-day job with a team of four
As a subcontractor we had little input into planning – we installed to the given design.
We were almost the last trade in the room. Floor and walls were already finished, so we had to work very cleanly.
The walls had to go in without damaging the floor or the folding walls, and the connection to the glass front had to fit exactly.
Because this is an electrical partition, extra safety systems were needed: earthed doors, contact switches and electric door locks. The doors only open once the test bay has been made safe.
Four of us built the new room in one full day while production continued. The client was able to install its test station shortly afterwards and can now test batteries safely and cleanly.


We keep your production running
Our service areas
Follow us on social media
Related guides for this project
About the author
Tobias Schott
Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance
A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. The project diary shows jobs his team has planned and carried out – without client names, but with everything there is to learn from them.