Commissioning: FAT, SAT and Levels 1 to 5 – the road to handover

By Tobias Schott  · 8-minute read · Updated October 2026

Commissioning is the documented proof that a facility has been built as designed and works as designed – and without that proof, no generator, cooling unit or power distribution board goes live in a data center. The word appears in almost every data center tender, in the general contractor’s programme and on the tags hanging from switchgear and generators. If you think of it as simply switching the plant on, you underestimate it: it is a testing process that runs for months, with fixed levels, test scripts and signatures.

For an installation contractor like us, this means that everything we move in, set in place and bolt down is checked again at every level. Below we explain what commissioning is, what Levels 1 to 5 involve, how FAT, SAT, trial runs and acceptance fit together, and what installation contributes.

What is commissioning?

Commissioning is a planned, staged process of testing and evidence. It shows that a facility has been correctly delivered, installed, started up and tested under load – and that it responds as designed together with all other systems. The short form is Cx; German documents often call it “Inbetriebnahme- und Abnahmeprozess”. The difference from a simple start-up is scope: commissioning begins with tests at the manufacturer’s works, ends with handover to operations and records every step.

The process is at its strictest in data center construction, because what a data center sells is availability. You cannot tell by looking whether a standby generator will start and pick up the load when the mains fail – you have to test it.

Key facts

What are commissioning levels 1 to 5?

Diagram: commissioning in five levels – from factory acceptance through installation, start-up and load testing to the integrated systems test
Five levels, one rule: no level starts until the previous one is closed with a signed record. Graphic: Omega Mounting

In data center construction, commissioning usually has five levels: Level 1 factory testing, Level 2 delivery and installation, Level 3 start-up, Level 4 performance under load and Level 5 integrated systems testing. Some owners add a design review before (Level 0) and a training and documentation stage after (Level 6); the logic stays the same. Each level answers one question. Only when the answer is documented does the next level begin.

LevelTypical nameQuestion answeredWhat must be in placeInstallation role
Level 1 – Factory acceptanceFactory Acceptance Test (FAT); when witnessed, Factory Witness Test (FWT)Does the unit deliver the specified performance at the factory?Factory test report, approved data sheets, release for shipmentNo test duty – we read the documents to know weight, centre of gravity and lifting points for the move-in
Level 2 – Delivery and installationDelivery and installation verification; often split into L2A (red tag: set in place) and L2B (yellow tag: ready to energise)Has the unit arrived undamaged, and is it set in place as designed?Goods-in inspection, evidence of placement and anchoring, alignment record, photosCore level for installation: move in, set in place, align, anchor, record torques
Level 3 – Start-upStart-up and pre-functional testCan the unit be switched on, and does it run on its own?Complete installation evidence, isolation and energisation plan, manufacturer’s start-up reportSupport: check anti-vibration mounts, pipework and covers; mechanical fitters on call
Level 4 – Performance under loadFunctional Performance Test (FPT)Does the individual system deliver its design capacity, and does it respond correctly to faults?Test script, load bank or heat load, measured data, signed recordMove in and set up load banks, fix mechanical faults immediately
Level 5 – Integrated systemsIntegrated Systems Test (IST)Does the whole facility respond to a mains failure exactly as the sequence of operations says?All individual systems signed off, snags closed, operator present as witnessStandby on site, removal of temporary installations, handover documentation
Technical drawing of the integrated systems test as a chain: simulated mains failure, switchover to standby power, generator start, cooling starting up and alarms reporting, with the installation team on call to readjust immediately
The mains failure is simulated – switchover, generator start, cooling and alarms run together while the installation team is on call. Graphic: Omega Mounting

The defining feature is the fixed sequence: nothing is energised until Level 2 is signed off, and no integrated systems test starts until Level 4 is complete. Many owners show the status on each unit with coloured tags added level by level – commonly red (installed), yellow (ready to energise), green (start-up done), blue (performance tested) and white (IST passed). If you can read the tag, you know what is still allowed on that equipment.

FAT, SAT, trial run, acceptance: how do the terms fit together?

FAT and SAT describe where a test takes place; trial run and acceptance describe its outcome – and all four map onto the five levels. Tenders often list them side by side without explaining how they relate.

Technical drawing of the commissioning chain from factory via transport, start-up and load test to the integrated systems test, with brackets showing where factory acceptance test, site acceptance test, test run and integrated systems test belong and acceptance as the legal act at the end
FAT and SAT name where the test takes place – test run and acceptance name its result. Graphic: Omega Mounting

In practice: a facility can pass all five levels and still not be legally accepted. Keeping the two apart avoids disputes over snags.

Noise measurement under full load – still from the measurement video
Functional test under full load: only the measurement shows whether the plant delivers what the design promises.
Aligned and ready for electrical connection
Set in place, aligned, documented – this is how installation hands a power distribution cabinet over to the next level.

What does installation contribute to commissioning?

Installation provides the evidence that the equipment sits exactly where the design says – without that evidence, the process does not get past Level 2. Our contribution is mechanical and documentary:

Technical drawing of the installation team's contributions to commissioning: evidence of position, clearances and anchoring, torque marked on the bolt and in the record, a punch list with open items and deadlines, and mechanics on call during the tests
Installation evidence, torque record, punch list and on-call support during the tests – that is what installation delivers to commissioning. Graphic: Omega Mounting

We are just as clear about where our scope ends: insulation tests on the system are carried out by our own qualified electricians, protection settings in the building network remain with the operator, and starting the control system with the manufacturer or system integrator. We handle the mechanical work and the system electrics and document both so that the next level can build on it – for international clients often in English.

What we pay attention to

In commissioning, the course of the installation work is decided long before the first test. This is what we keep an eye on:

Technical drawing of Commissioning with numbered check points: Factory documents, Document, Torque, Release, Punch items, Standby
Documents, photos, marked bolts, approvals, punch items, standby. Graphic: Omega Mounting

Where we use it

We mostly meet commissioning in data centers in the Rhine-Main region, at every one of the five levels. In Frankfurt am Main, a team of nine unloaded five heavy transports with generators and load banks in one working day. A 220-tonne-class mobile crane set them into a multi-storey steel structure – the load banks are the test equipment for Level 4. In Offenbach am Main, three fitters installed twelve double turbo silencers above the standby generators, followed by performance and noise testing under full load. For 160 power distribution cabinets in eight data halls, our team laser-surveyed and marked every position, before each cabinet was aligned and handed over to the electrical contractor. For our wider data center work, see our page Data center construction.

More technology explained

Technology explained

the plant most often at the centre of load testing and the integrated systems test.

Technology explained

the authorisation required before any work on a tagged unit.

Guide

the guide with the documentation checklist for installation work.

Need fitters who know this process?

Planning a project that requires commissioning at every level, and need fitters who know the process and document their work ready for inspection? We move the equipment in, set it in place and support the tests through to handover. The quickest way is a callback – tell us briefly about the project, the equipment and the timeframe.

Free, no-obligation callback

Tobias Schott, managing director of Omega Mounting GmbH, on a construction site in front of scaffolding

About the author

Tobias Schott

Managing director of Omega Mounting GmbH, Rodgau · more than 20 years of hands-on experience in installation and maintenance

A trained mechatronics technician, working in maintenance, servicing and industrial installation since 2004 – first alongside his father, and with Omega Mounting since 2012: from overhead conveyors in Frankfurt to the crane system in a new-build hall. He plans and leads lifting operations as an appointed person (AP) in data centers and on industrial sites in the Rhine-Main region, trains and examines operators of cranes, mobile elevating work platforms and telehandlers, and is a qualified occupational safety specialist. On jobs abroad he is known as the “German Troubleshooter” – the person you call when a site gets stuck. He learned what quality means from his father, not from a manual: Made in Germany as a standard for his own work, not a label. That is why quality comes first at Omega Mounting – ahead of speed and price. The Technology explained articles cover the equipment and techniques his team uses every day: what counts on site is in them – what only appears in the brochure is not.

Frequently asked questions

Level 2, the delivery and installation level. We move equipment in, set it in place, align and anchor it, and record torques and photos. In models that split Level 2, our scope ends at the red tag (L2A): the unit is rigged into place, properly anchored and inspected. From Level 3 onwards we keep mechanical fitters on call during start-up, load and integrated systems tests.

Yes, in some owners’ models. Level 0 is the design review before construction, checking that the design can be commissioned. Level 6 follows the integrated systems test and covers training and documentation for handover to operations. Levels 1 to 5 stay the same: factory testing, delivery and installation, start-up, functional performance testing and integrated systems testing.